Tuesday, 3/20 Accomplishments
AO2/Medusa finished installed plumbing and powered up
CAPS cross computer calibrations and systems checks
GT-CIMS staged shipping material and began to unpack
HR-AMS installed and conducted power checks and alignment
ISAF completed mechanical installation and began cabling
Shipment preparations

Wednesday, 3/21 Plans
A/C access 16:00-17:30
A02/Medusa continue checks and optimize
CAPS continue system checks & pack
GT-CIMS instrument lab check-outs
HR-AMS calibrations 
ISAF complete cabling and plumbing and finish installation
Shipment preparations continue