Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit espo.nasa.gov for information about our current projects.

 

2012-09-22

WFF: All times EDT

Sunday, 9/23
1520 AV-6 estimated landing time
1920 AV-6 estimated instrument aircraft access

Monday, 9/24
Hard Down Day
Next potential flight Wed 9/26, 0630 estimated takeoff time

DFRC: All times PDT

Sunday, 9/23
No AV-1 activity

Monday, 9/24
Possible instrument testing on AV-1; PIs be prepared to support from WFF

2012-09-21

(Note: there's a possibility of a change later this evening due to aircraft status, please check your emails).

WFF: All times EDT

Saturday, 9/22
AV-6 science flight (TS Nadine & P31L with lawnmower pattern)
1030 T-0 brief
1115 engine start
1300 takeoff time (estimated 25.5 hr duration)

Sunday, 9/23
1430 AV-6 estimated landing time
1830 AV-6 estimated instrument aircraft access

DFRC: All times PDT

Saturday, 9/22
AV-1 HIRAD fairing work

Sunday, 9/23
No AV-1 activity

2012-09-20

WFF: All times EDT

Friday, 9/21
0900-1500 AV-6 instrument aircraft access
1030 debrief from the 9/19-9/20 flight
1500-1700 AV-6 aircraft preflight

Saturday, 9/22
AV-6 science flight (TS Nadine with lawnmower pattern)
1300 estimated takeoff time (estimated 27.5 hr duration)

 

DFRC: All times PDT

Friday, 9/21
AV-1 safety review continues
AV-1 transit is not earlier than 9/28-9/29, see tentative best case schedule at http://espo.nasa.gov/missions/hs3/hs3-calendar/2012-09

Saturday, 9/22
TBD

2012-09-19

WFF: All times EDT

Thursday, 9/20
1545 AV-6 estimated landing time
1945 AV-6 estimated instrument aircraft access

Friday, 9/21
TBD

 

DFRC: All times PDT

Thursday, 9/20
Shuttle Endeavour visit, AV-1 no aircraft activity

Friday, 9/21
TBD

2012-09-18

WFF: All times EDT

Wednesday, 9/19
Media Day
AV-6 science flight (TS Nadine with lawnmower pattern)
     1200 T-0 brief
     1300 engine start
     1400 estimated takeoff time (estimated 25.5 hr duration)

Thursday, 9/20
1530 AV-6 estimated landing time
1730 AV-6 estimated instrument aircraft access

 

DFRC: All times PDT

Wednesday, 9/19
AV-1 safety review; no aircraft activity

Thursday, 9/20
TBD

2012-09-17

WFF: All times EDT

Tuesday, 9/18
0700-1300 AV-6 instrument aircraft access
1300-1500 AV-6 aircraft preflight
AV-1 no activity; pre-CST delayed beyond Tuesday, more info to follow

Wednesday, 9/19
AV-6 science flight (TS Nadine with lawnmower pattern)
1400 estimated takeoff time (estimated 26 hr duration)

 

DFRC: All times PDT

Tuesday, 9/18
AV-1 safety review; no aircraft activity

Wednesday, 9/19
TBD

2012-09-16

WFF: All times EDT

Monday, 9/17
AV-6 maintenance continues

Tuesday, 9/18
AV-1 pre-CST support from PMOF
      Ku testing in morning
      1200 AV-1 PIs at Stations ready to communicate to their instrument
AV-6 aircraft access / preflight

 

DFRC: All times PDT

Monday, 9/17
AV-1 APCS testing, etc. continues

Tuesday, 9/18
AV-1 Ku testing and pre-CST

2012-09-15

WFF: All times EDT

Sunday, 9/16
GH Crew Hard Down Day

Monday, 9/17
AV-6 maintenance continues

 

DFRC: All times PDT

Sunday, 9/16
GH Crew Hard Down Day

Monday, 9/17
AV-1 comm testing morning, pre-CST afternoon

2012-09-14

WFF: All times EDT

Saturday, 9/15
1000 estimated landing time
1400 estimated aircraft access

Sunday, 9/16
Hard Down Day

 

DFRC: All times PDT

Saturday, 9/15
Comms testing continues

Sunday, 9/16
Hard Down Day

2012-09-13

WFF: All times EDT

Friday, 9/14
Science Flight AV-6 (TS Nadine with lawnmower pattern)
0430 T-0 brief
0515 engine start
0615 takeoff time

Saturday, 9/15
0615 estimated landing time

 

DFRC: All times PDT

Friday, 9/14
KuSS and Iridium testing continues