Forecast Dry Run; August 6-16; See email sent to list serve on 7/30/13, titled 'HS3 Dry Run 2013'.
Please Note: Transits next week are planned for takeoff at ~7 pm PDT; land ~0800 EDT. There is a possibility of a longer flight due to weather, science goals, or range conflicts. Please plan accordingly. See GHOC and GHOC-E Instrument Team Staffing notes below.
DFRC UPDATE:
AV-6 Goals:
Pending: Nose camera lens installation and checkout
AV-1 Completed:
Instrument Post/Pre-flight and Aircraft Preflight
AV-1 Goals:
Pending: Nose camera lens installation and checkout
Thursday August 8: Range Flight
PIs not required
Engine start 0600
Take off 0700
Landing 1200
Friday August 9: shipment prep
WFF UPDATE:
AV-1 Goals:
Thursday August 8: Range Flight
PIs in GHOC-E 0830 EDT
Engine start 0900
Take off 1000
Landing 1500
Note: GHOC-E POR Staffing is optional after Takeoff + 2 hrs and prior to Landing – 2hrs, with the exception of any science or test activity (such as Drop Sonde launches, etc).