2012-10-02

WFF: All times EDT

Wednesday, 10/3
1100-1800 AV-1 pre-CST support from PMOF (Ku, IT, AV-1 instruments)
AV-6 Maintenance

Thursday, 10/4
AV-1 CST support from PMOF (Ku, IT, AV-1 instruments)
AV-6 Maintenance

Next possible AV-6 science flight Saturday, 10/6 (if suitable target)

DFRC: All times PDT

Wednesday, 10/3
0700-0800 AV-1 engine run
0800-1500 AV-1 pre-CST; pre-flight for CST

Thursday, 10/4
AV-1 CST

2012-10-01

WFF: All times EDT

Tuesday, 10/2
1000-1800 AV-1 testing and pre-CST support from PMOF (Ku, IT, AV-1 instruments)

Wednesday, 10/3
Possible AV-1 CST support from PMOF (TBD based on Tuesday's progress)
TBD AV-6 aircraft instrument access

Next possible AV-6 science flight Thursday, 10/4

DFRC: All times PDT

Tuesday, 10/2
0700-1500 AV-1 testing and pre-CST; begin pre-flight for CST (if time permits)

Wednesday, 10/3
Possible AV-1 CST (TBD based on Tuesday's progress)

2012-09-30

WFF: All times EDT

Monday, 10/1
1000-1800 AV-1 testing and pre-CST support from PMOF (Ku, IT, AV-1 instruments)

Tuesday, 10/2
Possible AV-1 CST support from PMOF (TBD based on Monday's progress)

Next possible AV-6 science flight Thursday, 10/4

DFRC: All times PDT

Monday, 10/1
0700-1500 AV-1 testing and pre-CST; begin pre-flight for CST (if time permits)

Tuesday, 10/2
Possible CST (TBD based on Monday's progress)

2012-09-29

WFF: All times EDT

Sunday, 9/30
AV-6 no aircraft instrument access

Monday, 10/1
1000-1800 AV-1 pre-CST support from PMOF (Ku, IT, AV-1 instruments)
TBD AV-6 aircraft instrument access

Next possible flight Wednesday, 10/3

DFRC: All times PDT

Sunday, 9/30
Hard Down Day

Monday, 10/1
0700-1500 AV-1 comms testing and pre-CST

2012-09-28

WFF: All times EDT

Saturday, 9/29
Work day for all except pilots (pilot down day)
1000-1800 AV-1 pre-CST support from PMOF (Ku, IT, AV-1 instruments)
AV-6 no aircraft instrument access

Sunday, 9/30
Flight planning for Tue flight
AV-6 no aircraft instrument access

Next possible flight Tuesday, 10/2

DFRC: All times PDT

Saturday, 9/29
0700-1500 AV-1 comms testing and pre-CST

Sunday, 9/30
Hard Down Day

2012-09-27

WFF: All times EDT

Friday, 9/28
0800-1000 AV-6 aircraft instrument access
1030 Debrief from 9/26-27 flight
No forecasting briefings

Saturday, 9/29
Work day for all except pilots (pilot down day)
Possible AV-1 support activities from PMOF -- Ku, IT, AV-1 instruments

Next possible flight Tuesday, 10/2

DFRC: All times PDT

Friday, 9/28
AV-1 final avionics work and power on aircraft

Saturday, 9/29
Possible AV-1 activity

2012-09-26

WFF: All times EDT

Thursday, 9/27
0815 AV-6 estimated landing time
1145 AV-6 estimated aircraft instrument access
TBD flight debrief
No forecasting briefings

Friday, 9/28
TBD AV-6 aircraft instrument access
No forecasting briefings

Next possible flight Tuesday, 10/2

DFRC: All times PDT

Thursday, 9/27
AV-1 limited avionics activity due to AV-6 flight

Friday, 9/28
AV-1 final avionics work and power on aircraft

2012-09-25

WFF: All times EDT

Wednesday, 9/26
AV-6 Science flight (TS Nadine with lawnmower pattern)
0430 T-0 brief
0515 engine start
0630 takeoff

Thursday, 9/27
0815 estimated landing time
1145 estimated aircraft instrument access

DFRC: All times PDT

Wednesday, 9/26
limited AV-1 avionics activity due to AV-6 flight

Thursday, 9/27
limited AV-1 avionics activity due to AV-6 flight

2012-09-24

WFF: All times EDT

Tuesday, 9/25
0700-1130 AV-6 aircraft instrument access
1030 Debrief from 9/22-23 flight
1200-1400 AV-6 aircraft preflight
TBD T-1 Briefing

Wednesday, 9/26
AV-6 Science flight (TS Nadine with lawnmower pattern)
0615 estimated takeoff time (26 hr duration)

DFRC: All times PDT

Tuesday, 9/25
AV-1 Limited avionics support due to AV-6 GHOC Flight Prep

Wednesday, 9/26
AV-1 cabin pressurization testing; no AV-1 avionics activity due to AV-6 flight

2012-09-23

WFF: All times EDT

Monday, 9/24
Hard Down Day

Tuesday, 9/25
0700-1130 AV-6 aircraft instrument access
1030 Debrief from 9/22-23 flight
1200-1400 AV-6 aircraft preflight
TBD T-1 Briefing

DFRC: All times PDT

Monday, 9/24
AV-1 wiring, APCS, and HIRAD fairing work (no power on aircraft until Avionics is ready for it)

Tuesday, 9/25
AV-1 HIRAD fairing work; possible instrument testing in afternoon -- PIs be prepared to support from WFF