Tuesday, August 22 Accomplishments
- SP2, ISAF, AO2/Medusa and CAFS installed
- Egress training
- Shipping preparations
Wednesday, August 23 Plans
- 06:00-18:30 Power checks, HR-AMS installation
- Pack cylinders for air shipment
Friday, August 18
All first wave instruments (NOyO3, QCLS, DLH, Picarro, TOGA, MMS, PALMS, AMP, ATHOS & SAGA), with the exceptioin of CAFS, installed
All power checks, with the exception of DLH, successfully completed
No issues
Saturday, August 19
First wave teams departed
Sunday, August 20
Second wave teams arrive
Monday, August 21
07:00 Badge office open for renewal of expired badges
06:00-15:00 A/C crew will work 9 hour days M-Th (Friday RDO)
QCLS, NOyO3 and Picarro bolted in, SAGA partially installed Wednesday
Tuesday, August 15
06:00-14:30 Aircraft access (overtime possible if warranted)
13:00 Meeting in lab
13:30 Egress training (every Tuesday and Thursday @ 13:30)
The AFRC crew is shorthanded this week so it will be 8 hour days of aircraft access with overtime possible if warranted. Saturday (819) is a possibility if warranted. Next week (8/21) the crew will go to the 9/80 schedule and the following week (8/28) they will work two shifts.
ATom Plan of the Day
Saturday, August 6th:
ATom Plan of the Day
Friday, 8/5
Saturday, 8/6