HS3 07/28/14 Daily Schedule

Overview:
   AV-1 Ready for CST – Science Team’s on scheduled break from AFRC/WFF
   AV-6 Integ. on schedule
Today’s Accomplishments:
   AV-6 Outdoor Testing
    o   S-HIS - complete (pic)
    o   CPL - complete
    o   AVAPS - in work
  AV-1 Maintenance (pic)
The Plan for Tuesday (all times PDT):
   0630: AV-6 Outdoors with Power
    o   0630: AVAPS power-on with support from WFF
        - AVAPS @ WFF support at 0930 EDT
    o   Primary initial GH Data-IT Activity will be with:
        - GHIS
         -Camera Systems
After Data-IT completes their initial activity with core systems - they WILL want to commence additional testing to possibly include Combined Instrument Testing... So S-HIS and CPL Teams should plan on supporting the continuation of AFRC and WFF GHOC-E test activity starting at ~0730 PDT (1030 EDT). Time to be determined by the Data-IT Team.
    o   1500: Power-down aircraft
    0800: HS3 Tech Brief
Outlook:
    Wed: AV-6 Outdoor Testing continues
    o   Possible Pre-CST
Thursday: AV-6 Pre-CST
Friday: Contingency

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.