HS3 07/25/14 Daily Schedule

Overview:

AV-1 Integration/Test completed on schedule – ready for CST-prep on 11Aug

AV-6 Integ. on schedule – Outdoor Satcom testing w/WFF starts Monday

 Today’s Accomplishments:

AV-1 Science Integ/Test activity ends

    o   HIWRAP data-file download

    o   Aircraft jacked for gear maint. (pic)

    o   Science Flight-prep starts: Monday, 11Aug (see below note)

AV-6 Wt & Balance

    o   CPL power harness expanded to EIP-4

    o   CPL Testing completed

Completed Daylight Nose Cam relocation

The Plan for Saturday:

AV-6 Avionics harness tie-down activity, No Power on Aircraft

Outlook:

Monday @ AFRC: AV-6 Outdoor Testing (all times PDT):

    o   0600 – 0900: Aircraft fueling

    o   1000 – 1200: Power-on, Data-IT Network/System Configuration

    o   1200 – ~1430: PI’s support Satcom Testing of Inst’s w/GHOC-E

Monday @ WFF: AV-6 Support in GHOC-E (all times EDT):

    o   0830: Badging, if needed

    o   0900: Scan Laptops, if required

    o   0930: COMSEC Briefing

    o   1000: Software download/install, if required

    o   1200: Lunch (yum)

    o   1400 – 1500: Be available (in case IT ready to start Satcom early)

    o   1500 - ~1730: PI’s in GHOC-E for Inst. Satcom Testing

Tues-Wed: Continue outdoor testing w/GHOC-E

Thurs: Pre-CST

Monday Aug-11th – Special Note to AV-1 Teams:

    o   AFRC: 0630 PDT: HIRAD req’d for Install in GH Hangar

0800: HAMSR & HIRAD PI’s Support Data-IT Retest (HIWRAP too, if desired)

    o   WFF: Need to AV-1 PI’s TBD (AFRC Testing may only be in Hangar)

 

Continue to monitor this Daily Msg. for info

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.