HS3 07/22/14 Daily Schedule

Overview:

AV-1 Testing on schedule

AV-6 Integration continues

Today’s Accomplishments:

AV-1 Outdoor testing with GHOC-E participation (pic)

      o   HAMSR - complete

      o   HIRAD – complete

      o   HIWRAP – complete

AV-6 integration activity started

      o   S-HIS – installed (pic)

      o   AVAPS – installed (pic)

      o   CPL – SIL Bench in work

The Plan for Wednesday is (all times PDT):

0630 (0930 EDT): Aircraft outdoors with Power (GHOC-E support begins)

0645: Pre-CST to begin (may be delayed, per Data-IT)

0730: Payload Cage meeting of Leads

0800: NHK Japanese Film Crew arrives in AFRC Hangar

HIRAD RF Test: To be performed after Pre-CST, time/temp allowing

Installation of CPL in AV-6

The Plan for Thursday is:

WFF COMSEC Training at AFRC (Time TBA)

AV-1: HIRAD RF Test (if not completed Wednesday

           o   HIRAD Removal per Aircraft Maint. required

AV-6: Hangar Data-IT Testing

Outlook:

AFRC:

          o   Friday: AV-1 TBD, AV-6 Wt/Bal

          o   No activity planned for Sat & Sun

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.