IMPACTS 01/12/20 Mission Daily Schedule

IMPACTS General
Coordinate with ESPO if you have any questions and/or concerns. All times below are Eastern Standard Time.

MONDAY, JAN 13
09:00-10:00: Daily Briefing (Wallops W162; Webex/Telecon)

TUESDAY, JAN 14
*10:00:11:00*: Daily Briefing (Wallops W162; Webex/Telecon)

WEDNESDAY, JAN 15
09:00-10:00: Daily Briefing (Wallops W162; Webex/Telecon)
10:00-11:00: All-Hands Mission Kick-Off & Safety Briefing (WFF/ Hunter AAF separate meetings)

IMPACTS P-3 - Wallops

MONDAY, JAN 13
No Fly Day
08:00-14:30: Aircraft access with power

TUESDAY, JAN 14
Media Day at NASA WFF
Safety Brief (TBD new folks only)
08:00-11:00: Aircraft access with power
Test Flight Day (Timing TBD)

WEDNESDAY, JAN 15
08:00-14:30 Aircraft access with power

IMPACTS ER-2 - Hunter

MONDAY, JAN 13
Day & Night Proficiency flight
Equipment arrives / Begin Hangar Setup

TUESDAY, JAN 14
Finish Hangar Setup

WEDNESDAY, JAN 15
12:00: ER-2 Transit to Hunter