HS3 07/24/14 Daily Schedule

Overview:

AV-1 and AV-6 integration and testing is on schedule.

 

Today’s Accomplishments:

AV-1 HIRAD RF Test complete

o   HIWRAP waveform refinement activity

o   HIRAD & HAMSR removal for camera work & A/C maint.

AV-6 Hangar IT Testing

o   AVAPS Testing complete

o   S-HIS Testing complete

o   CPL Installed and Testing in work

H.S. Student visit

 

The Plan for Friday (all times PDT):

AV-6  Wt. & Balance

o   AV-6 Hangar IT Testing (CPL) in PM

AV-1 HIWRAP testing (PI request)

o   Camera Data-IT Testing

 

Outlook:

Saturday Avionics activity on AV-6 (No Power on Aircraft)

Monday @ AFRC: AV-6 Outdoor Testing

o   Schedule TBD (PIs should be present starting at 0830)

Monday @ WFF:

o   0730: Badging, if needed

o   0800: Scan Laptops

o   0930: COMSEC Briefing

o   1000 – 1100: Software Downloads/installs, if required

o   1100 – 1130: Eat Lunch

o   1130: Begin Satcom Testing in GHOC-E

Special Monday Aug-11th Note to AV-1 Teams:

o   AFRC: 0630 Outdoor Testing of aircraft (PI’s support req’d)

o   WFF: 0930 GHOC-E Support (HIRAD, HIWRAP, HAMSR PI’s needed)

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.