HS3 07/16/14 Daily Schedule

Overview:

AV-1 Integration and aircraft activity continue on schedule.

 

Today’s Accomplishments:

AV-1 integration activity is complete

o   HAMSR installed

o   HIRAD installed

o   HIWRAP installed

Aircraft ready for Wt. & Balance

The Plan for tomorrow (Thursday) is:

0730: Payload Cage meeting of Leads and PI’s

Wt & Balance

Fuel aircraft and reweigh

Avionics prep for power (see Friday)

Instrument teams requested to remain in Hangar to support Avionics activity

 

The Plan for Friday is:

Hangar IT Testing of instruments (0700 - 1500)

 

Outlook:

No activity planned for Saturday or Sunday

Monday +: AV-1 Outdoor Satcom/GHOC-E Data-IT testing of Instrument

Monday +: AV-6 Instrument Teams arrive, Integration activity

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.