HS3 07/14/14 Daily Schedule

Overview:

HS3 ‘14 begins today at AFRC and WFF.

 

Today’s Accomplishments:

Dana Tanks arrived at WFF

At AFRC, HIWRAP, HIRAD, and HAMSR teams arrived and began pre-integration testing

o   HAMSR passed SIL Bench

o   HIRAD SIL Bench started

COMSEC Training of PI’s at AFRC

The Plan for tomorrow (Tuesday):

0730 Payload Cage meeting of Leads and PI’s

HAMSR installation on aircraft

HIRAD outdoor sky radiation test

HIRAD completes SIL Testing, possible installation

HIWRAP SIL Bench Test

 

The Plan for Wednesday:

Installation of HIWRAP and HIRAD

Begin Hangar IT if time allows

Prep aircraft for Wt./Bal

 

Outlook:

Thursday AM is AV-1 Wt/Balance

Thursday PM is Hangar IT with all instruments

Friday all day: Hangar IT with all instruments

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.