Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

2014-02-07

ATTREX  GH Overview:

- After the scrub today, instruments needing off-aircraft testing were removed

- OmniSTAR testing and consultation with NGC and USAF continues.

- Bernie Luna will assume responsibility as onsite ATTREX Proj. Mgr starting tomorrow.

 

Today’s Activities:

- Science Flight scrubbed due to OmniSTAR issues on the aircraft

- OmniSTAR Testing is being performed this afternoon on a USAF GH for comparison info

- AV-6 outdoor OmniSTAR testing continues this evening

  o All aircraft panels and Z-25 Fairing to be secured on aircraft in case of rain while outdoors

 

The Plan for tomorrow (Saturday) is:

- 0700: Normal “0730” daily morning meeting of Leads for GH, ESPO, Science in the Hangar

- All-hands Science Team Mtg – see Eric’s e-mail. Tentative time: 0830, (Conf. Rm., Building 18006, Rm 15)

- Note: Due to the option of more outdoor OmniSTAR testing, aircraft access is likely very limited for instrument teams.

  o Anyone needing access, please contact Dave F. so we can plan for it.

 

Outlook:

- A replacement  NASA GH OmniSTAR unit will arrive in Guam tomorrow night.

  o After installation, aircraft outdoor testing will occur.

- The next flight date will be set once the OmniSTAR issue is resolved.

2014-02-06

ATTREX  GH Overview:

-Proceeding to another science flight attempt tomorrow, 0700 Takeoff.


The schedule for the remainder of today is:

-1230: Aircraft returns to Hangar

-Zone-25 will be removed for standard post-flight gas valve turn-off of DLH and HUPCRS instruments

-1700: 2nd-shift Crew arrives

-HUPCRS access as requested with external power

-Access with Crew permission, after they arrive on duty

-Aircraft to remain in pre-flighted condition – no instrument access except as mentioned


The Schedule for Friday is:

-0000 – 0300 ChST: Day-of-Flight Instr. Preflight by PCRS, Mini-DOAS, and DLH.

-Instrument Team hands-off at 0300

-0500: T-0 Briefing with GH Team & Science Leads (Building 18006, Rm 15)

-0545: Staffing of PMOF and GHMOF by Instr. Teams and Flt Crew

-0600: Engine Start

-0700 (2100 Z, Wed): Take-off for a planned 14-hr flight

-2100 (1100 Z, Thurs): Est. Landing time.


The Current Plan for Saturday is for Aircraft and Instrument Post-flight:

-0600 - ~1100: GH Crew post-flights aircraft (weight, fuel, engine wash, weigh, de-panel)

-~1100 - 1300: Access to instruments with aircraft power and Data-IT support

2014-02-05

ATTREX  GH Overview:

- Proceeding to a planned Science flight tomorrow, 0700 Takeoff.

- Pics from recent activities.

 

The Schedule for Thursday is:

- 0000 – 0300 ChST: Day-of-Flight Instr. Preflight by PCRS, Mini-DOAS, and DLH.

  o Instrument Team hands-off at 0300

- 0500: T-0 Briefing with GH Team & Science Leads (Building 18006, Rm 15)

- 0545: Staffing of PMOF and GHMOF by Instr. Teams and Flt Crew

- 0600: Engine Start

- 0700 (2100 Z, Wed): Take-off for a planned 14-hr flight

- 2100 (1100 Z, Thurs): Est. Landing time

 

Issue of Note:

- The Payload Ku Satcom system is still experiencing a fault and is likely to not function during the flight.

  o The flight will proceed as planned with the GHMOF being provided MMS and MTP Data via Payload Iridium.

  o These 2 instruments have been given Network Traffic priority over the system for this purpose.

 

The Current Plan for Friday is for Aircraft and Instrument Post-flight:

- 0600 - ~1100: GH Crew post-flights aircraft (weight, fuel, engine wash, weigh, de-panel)

- ~1100 - 1300: Access to instruments with aircraft power and Data-IT support

2014-02-04

ATTREX  GH Overview:

- Instrument & Aircraft Pre-flight tomorrow for a planned Thursday flight, 0700 Takeoff.

 

The Schedule for tomorrow is:

- 0730 - 1030: Outdoor testing of Ku System

- 1000: T-1 Briefing with GH Team & Science Leads (Building 18006, Rm 15)

- 1100 – 1300: Instrument Preflight

  o Instrument Team hands-off at 1300

- 1300 – 1600: Aircraft Preflight

 

The Schedule for Thursday is:

- 0000 – 0300 ChST: Day-of-Flight Instr. Preflight by PCRS, Mini-DOAS, and DLH.

  o Instrument Team hands-off at 0300

- 0500: T-0 Briefing with GH Team & Science Leads (Building 18006, Rm 15)

- 0545: Staffing of PMOF and GHMOF by Instr. Teams and Flt Crew

- 0600: Engine Start

- 0700 (2100 Z, Wed): Take-off for a planned 14-hr flight

- 1900 (0900 Z, Thurs): Est. Landing time

 

The Current Plan for Friday is for Aircraft and Instrument Post-flight:

- 0600 - ~1100: GH Crew post-flights aircraft (weight, fuel, engine wash, weigh, de-panel)

- ~1100 - 1300: Access to instruments with aircraft power and Data-IT support

2014-02-04

Overview:

- Ku testing has confirmed the need for a Ku-HPA replacement, which will begin immediately.

- Next flight is now pushed to Thursday, 0700 takeoff.

 

Today’s activities:

- Performed Engine Wash, and outdoor OmniSTAR and Ku testing

- Reviewed DFRC/NGC data analysis of the Aborted T.O. with GH Chief Engineer

- KU HPA replacement to begin on aircraft

- MTP to be re-installed on aircraft on non-interference with Ku activity

 

The Plan for tomorrow (Wednesday) is:

- 0600 – TBD: Complete KU HPA replacement and testing

- ~noon (TBD): Instrument Pre-flight activity (2-hr period..  time’s TBD, standby for notice)

 

The Plan for Thursday is:

- 0000 – 0300: Day-of-Flight Instr. Preflight by PCRS, Mini-DOAS, and DLH.

  o Instrument Team hands-off at 0200

- 0500: T-0 Briefing with GH Team & Science Leads (Building 18006, Rm 15)

- 0545: Staffing of PMOF and GHMOF by Instr. Teams and Flt Crew

- 0600: Engine Start

- 0700: Take-off for 14-hr flight (2100 Z, Wed)

- 2100: Estimated Landing time (1100 Z, Thurs)

- (Except for very limited Z-25 access to turn-off gases - there will be no other instrument access after the landing)

 

Outlook:

- Friday is post-flight on instruments

- Assuming flight is Thursday, proposed Science Flt 2 will be 72 hrs after Science Flt 1

2014-02-03

Today's accomplishments:
- Down Day for GH Crew
- Consulting with L-3Com on Ku Fault
- Mission Planning activity
 
Tomorrow's Plan
- 0600: Aircraft moved back to Hangar 4
  o KU Waveguide maint.
- 0730: Aircraft outdoors for:
  o Engine Wash
  o Ku SatCom Testing 
  o Additional OmniSTAR Characterization Testing
- 1000: Aircraft back to Hangar
Note: two possible paths after 1000:
  o If Ku testing is unsuccessful, the KU HPA will need to be replaced, which will take several hours and require outdoor testing. L3-Com has advised us this is a likely scenario. In this case, the proposed Wed Flt will need to move to Thursday, and Inst. Preflight activity will move to Wed.
  o If Ku testing is successful we will begin Instr. Preflight activity at 1030 for a proposed Wed. flt.
 
Standby for an update at 1000 hrs on this and the other two issues being worked:
- Reviewing NGC's  analysis and the GH Team's assessment of the Takeoff abort with DFRC Management.
- Status on the installation and config of the GHMOF backup Services Computer that has arrived at AAFB from DFRC.

2014-02-02

Today’s activities:

- Post-flight completed with all instruments

- Performed Engine Wash, and outdoor OmniSTAR and Ku testing

- Reviewed NGC data analysis of the Aborted T.O. and downloaded HDVis images from the aircraft.

- GH moved to USAF GH Hangar until Tues morning.

 

The Plan for tomorrow (Monday):

- Hard Down Day for the GH Crew.

 

The Plan for Tuesday is:

- 0700: Aircraft retrieval from USAF GH Hangar

- ~0800 – ~1400: Instrument Pre-flight activity and Aircraft Maintenance & Pre-flight

  o Actual Instrument time with Power & Data-IT is TBA

 

The Plan for Wednesday (subject to change):

- Next Science Flight – Details TBA

 

Outlook:

- Thursday is backup to Wed’s flight date if any issues delay the flight.

2014-02-01

ATTREX  GH Overview:

- Instrument post-flight with external power, as needed.

- Reviewing data from today’s activity with NGC assistance

 

The Plan for tomorrow (Sunday) is:

- 0800 – 1000: Aircraft outside for OmniSTAR Testing

- 1030 – 1230: Instrument post-flight with aircraft power and Data-IT support

- ~1300: Aircraft towed to USAF GH Hangar through Tuesday 0600.

 

The Plan for Monday) is a Hard Down Day for the GH Crew

 

The Plan for Tuesday (subject to change):

- Preflight Instruments with Aircraft Power and Data-IT

2014-01-31

ATTREX  Instrument Pre-flight today at 1200 – 1330 (ChST):
    The aircraft gear maintenance activity is going well, and we have set the period noon-1330 for Instrument Pre-flight activity today.
    If your instrument needs any pre-flight activity today – please come to the Hangar by noon.
    Thanks.
 
We will announce the Day-of-Flight Schedule in a few hours…

2014-01-29

ATTREX  GH Overview:

- Due to continued and forecast rain and low ceilings at AAFB, Guam,

and an issue with a computer in the GHMOF, the flight is cancelled for today and tomorrow.

 

The Schedule for today – aircraft is available for instrument activity as needed:

- The aircraft is available for instrument activity as needed through 1600.

- ATTREX Science Mtg at 1300 in Building 18006, Rm 15

- GH SSWG members in Guam to initiate review of GHMOF items

 

The Schedule for tomorrow (Thursday) is aircraft maintenance and pre-flight:

- Aircraft will be on jacks and generally unavailable for science instrument activity in the morning, early afternoon

- Instrument Pre-flight activity is estimated to be mid-late afternoon

 

Assuming GHMOF is cleared – the Schedule for Friday is a Noon Takeoff (actual schedule TBD): 

Current proposed schedule is:

- 0500 – 0800 ChST: Day-of-Flight Instr. Preflight by PCRS, Mini-DOAS, and DLH.

  o Instrument Team hands-off at 0800

- 1000: T-0 Briefing with GH Team & Science Leads (Building 18006, Rm 15)

- 1045: Staffing of PMOF and GHMOF by Instr. Teams and Flt Crew

- 1100: Engine Start

- 1200: Take-off for a planned 14-hr flight

- 0200: Est. Landing time, Thursday