Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

2014-01-28

ATTREX  GH Overview:

- Due to continued rain and low ceilings at AAFB, Guam,

today’s flight schedule is postponed 24-hrs… see schedule below.

 

The Schedule for today – Aircraft stays in a “Preflight” condition:

- The GH Crew will drop Z-25 Fairing in prep for tomorrow’s Day-of-Flight Preflight activity

- No other aircraft support is expected.

- Science Note: Look for an announcement of an ATTREX Science Mtg (tomorrow if the flight is again postponed)

 

The Schedule for tomorrow (Wednesday) is a Noon Takeoff:

- 0500 – 0800 ChST: Day-of-Flight Instr. Preflight by PCRS, Mini-DOAS, and DLH.

  o Instrument Team hands-off at 0800

- 1000: T-0 Briefing with GH Team & Science Leads (Building 18006, Rm 15)

- 1045: Staffing of PMOF and GHMOF by Instr. Teams and Flt Crew

- 1100: Engine Start

- 1200: Take-off for a planned 14-hr flight

- 0200: Est. Landing time, Thursday

 

The Current Plan for Thursday is for Aircraft and Instrument Post-flight:

- 0700 - ~1200: GH Crew post-flights aircraft (weight, fuel, engine wash, weigh, de-panel)

- ~1200 - 1400: Access to instruments with aircraft power and Data-IT support

2014-01-27

ATTREX  GH Overview:

- Instrument & Aircraft Pre-flight today.

- There is no ATTREX Science Team Mtg today.

- With the likelihood of continued rain and low ceilings at AAFB, Guam,

the flight tomorrow is postponed 6 hours… see schedule below.

 

The Schedule for tomorrow (Tuesday) is a Noon Takeoff:

- 0500 – 0800 ChST: Day-of-Flight Instr. Preflight by PCRS, Mini-DOAS, and DLH.

  o Instrument Team hands-off at 0800

- 1000: T-0 Briefing with GH Team & Science Leads (Building 18006, Rm 15)

- 1045: Staffing of PMOF and GHMOF by Instr. Teams and Flt Crew

- 1100: Engine Start

- 1200: Take-off for a planned 14-hr flight

- 0200: Est. Landing time, Wednesday

 

The Current Plan for Wednesday is for Aircraft and Instrument Post-flight:

- 0700 - ~1200: GH Crew post-flights aircraft (weight, fuel, engine wash, weigh, de-panel)

- ~1200 - 1400: Access to instruments with aircraft power and Data-IT support

2014-01-26

ATTREX  GH Overview:

- Science Flight is postponed to Tuesday 0600 ChST due to wind conditions here at Guam today.

 

The Plan for tomorrow (Sunday) is:

- Decision was made at 0730 to postpone the preflight to tomorrow due to weather conditions.

- The aircraft remains in the USAF GH Hangar - No aircraft access of any kind today

 

The Plan for Monday is for Instrument and Aircraft Preflight:

- 0615 – Aircraft OmniSTAR testing outdoors prior to return to Hangar

- 0900 – 1200: Instrument Team Pre-flight access with Power.

  o Please start at 0900 – hands off at 1200.

- 1200 – 1500: Aircraft Preflight by GH Crew

- (TBA): T-1 Briefing for First Science Flight

 

The Plan for Tuesday (subject to change) is:

- 2300 – 0200: Day-of-Flight Instr. Preflight by PCRS, Mini-DOAS, and DLH.

  o Instrument Team hands-off at 0200

- 0400: T-0 Briefing with GH Team & Science Leads (Building 18006, Rm 15)

- 0445: Staffing of PMOF and GHMOF by Instr. Teams and Flt Crew

- 0500: Engine Start

- 0600: Take-off for 14-hr flight (noon, Thursday PST)

- 2000: Estimated Landing time (0200, Friday PST)

2014-01-24

ATTREX  GH Overview:

- Science Flight postponed to Monday 0600 ChST due to wind conditions here at Guam.

 

The Plan for tomorrow (Saturday) is:

- Hard Down Day for GH Team

  o No aircraft access of any kind

 

The Plan for Sunday is for Instrument and Aircraft Preflight:

- UPDATED: 0800 – 1100: Instrument Team Pre-flight access with Power.

  o Please start at 0800 – hands off at 1100.

- UPDATED: 1100 – 1500: Aircraft Preflight by GH Crew

- (TBA): T-1 Briefing for First Science Flight

 

The Plan for Monday (subject to change) is:

- 2300 – 0200: Day-of-Flight Instr. Preflight by PCRS, Mini-DOAS, and DLH.

  o Instrument Team hands-off at 0200

- 0400: T-0 Briefing with GH Team & Science Leads (Building 18006, Rm 15)

- 0445: Staffing of PMOF and GHMOF by Instr. Teams and Flt Crew

- 0500: Engine Start

- 0600: Take-off for 14-hr flight (noon, Thursday PST)

- 2000: Estimated Landing time (0200, Friday PST)

 

Please contact Dave F., or Mike C., if you have any questions.

2014-01-23

ATTREX  GH Overview:

- Instrument and Aircraft Pre-flight.

- Ready for first Science Flight

 

Today’s Accomplishments:

- Preflight of all instruments and aircraft.

- GH Team T-1 Briefing

- ATTREX Science Team Meeting

- Fire Watch Training for DFRC GH Team by AAFB Fire Dept.

 

The Plan for tomorrow (Friday) is:

- 2300 – 0200: Day-of-Flight Instr. Preflight by PCRS, Mini-DOAS, and DLH.

  o Instrument Team hands-off at 0200

- 0400: T-0 Briefing with GH Team & Science Leads (Building 18006, Rm 15)

- 0445: Staffing of PMOF and GHMOF by Instr. Teams and Flt Crew

- 0500: Engine Start

- 0600: Take-off for 14-hr flight (noon, Thursday PST)

- 2000: Estimated Landing time (0200, Friday PST)

- (There should be no expectation of instrument access after the landing)

 

The Plan for Saturday (subject to change) is:

- 0600 - ~1100: GH Crew post-flights aircraft (weight, fuel, engine wash, weigh, de-panel)

- ~1100 - 1400: Access to instruments with aircraft power and Data-IT support

- ~1500: Aircraft towed to USAF GH Hangar through Monday 0600.

 

Please contact Dave F., or Mike C., if you have any questions.

2014-01-22

GH Overview:
- Rain, Rain… (Deluge, deluge) go away.
- Pics to prove the point.
 
Today’s Accomplishments:
- Final activity by Instrument Teams prior to preflight for first Science Flight
- Some teams have completed their pre-flight activity.
- Announcement of a 1-day delay in the Science Flt.
 
The Plan for tomorrow (Thursday) is:
- 0800 – 0945: Req’d Engine wash by Crew
- 1000 – 1300: Instrument Team Pre-flight access with Power.
  o Please start at 1000 – hands off at 1300.
- 1300 – 1600: Aircraft Preflight by GH Crew
- 1400: Science Team Meeting
- (TBA): T-1 Briefing for First Science Flight
 
The Current Schedule for Flight Day (Friday) is:
- 2300 – 0200:  Special Day-of-Flight Instr. Preflight by PCRS, Mini-DOAS, and DLH.
  o Instrument Team hands-off at 0200
- 0400: T-0 Briefing with GH Team & Science Leads
- 0445: Staffing of PMOF and GHMOF by Instr. Teams and Flt Crew
- 0500: Engine Start
- 0600: Take-off
- 2000: Estimated Landing time (14-hr flight)

2014-01-21

ATTREX  GH Overview:

- Instrument and GH Team continue to prepare for the first Science Flight

- Pics of some of today’s activity in the Instrument Trailers…

 

Today’s Accomplishments:

- Final activity by Instrument Teams prior to preflight for first Science Flight

- The Hawkeye Team (with Avionics and Data-IT support) successfully implemented and tested the new MPCS I.L. control of their Heaters.

- Some teams completed their preflight activity on the aircraft.

- Science Team Meeting

 

The Plan for tomorrow (Wednesday) is:

- 0800 – 0945: Req’d Engine wash by Crew

- 1000 – 1300: Instrument Team Pre-flight access with Power.

  o   Please start early – hands off at 1300.

- 1300 – 1600: Aircraft Preflight by GH Crew

 

The Tentative Plan for Flight Day (to be confirmed by 1000 tomorrow) is:

- 2300 – 0200:  Special Day-of-Flight Preflight by PCRS, Mini-DOAS, and DLH.

  o Instrument Team hands-off at 0200

- 0400: T-0 Briefing with GH & Science Leads

- 0445: Staffing of PMOF and GHMOF by Instr. Teams and Flt Crew

- 0500: Engine Start

- 0600: Take-off

- 2000: Estimated Landing time (14-hr flight)

2014-01-20

ATTREX  GH Overview:

- There will be a 24-hr postponement of the first Science flight due to the need for NGC Engineering to perform an analysis to clear the Hawkeye Pylon mount for this flight.

- The GH Team expects the first Science Flight to now occur on Thursday morning (Guam time).

 

The Plan for today (Tuesday, ChST) is NOW:

- 1000: Instrument Team Pre-flight access with Power and Data-IT support.

  o All instrument teams needing on-aircraft time are requested to perform their access this morning if possible.

  o Please contact Dave F., or Dave J., with specific needs regarding Aircraft Power or Data-IT

- 1400: ATTREX Science Meeting (see Eric’s e-mail for location)

 

The Plan for tomorrow (Wednesday, ChST):

- 0800 - 1000: Aircraft outdoors for req’d engine wash procedure

- 1000 – 1300: Instrument Team Pre-flight access with Power and Data-IT support.

  o All instrument teams needing on-aircraft time are requested to perform their access this morning if possible.

  o Please contact Dave F., or Dave J., with specific needs regarding Aircraft Power or Data-IT

 

Outlook

- The next Science Flight is tentatively scheduled for Thursday 23Jan’14

  o Currently planned Takeoff time: 0600 ChST for a 14 hr flight.

- Please contact Dave F., or Dave J., if you have any questions.

2014-01-19

ATTREX  GH Overview:

-  Preparations continue for the first Science flight.

 

Today’s Accomplishments:

-  Power Pallet data download

-  Hawkeye wiring modification to enable Payload Interlock Circuit control of heaters

-  Aircraft Payload System Satcom testing completed

-  Science Mission and Pilot Flight Planning continues (see pics)

 

The Plan for tomorrow (Tuesday, ChST) is:

-  0730 ChST: Leads Meeting in the Hangar to discuss open items

-  0800 – 0945 ChST: Aircraft outdoors for engine run and wash

- 1000: Instrument Team Pre-flight access with Power.

  o   All instrument teams need to begin on-aircraft inst. preflight at ~1000.

  o   Please contact Dave F., or Dave J., with specific needs regarding Aircraft Power or Data-IT

- 1300 – 1600: Aircraft Preflight by Crew

- 1400: ATTREX Science Meeting (see Eric’s e-mail for location)

 

Outlook

- The next Science Flight is tentatively scheduled for Wednesday 22Jan’14

  o   This will be confirmed at the 0730 meeting tomorrow.

  o   Any change will be immediately communicated via this listserve.

  o   Currently planned Takeoff time: 0600 ChST for a 14 hr flight.

- Please contact Dave F., or Dave J., if you have any questions.

2014-01-19

ATTREX GH Overview:

-   Next Science Flight Takeoff currently scheduled for Wed 22Jan’14

 

Today’s Accomplishments:

-   Down Day – no aircraft access

 

The Plan for tomorrow (Monday ChST) is:

-   0700 – 1230 ChST:  Instrument Team access to Aircraft, with Data-IT & Aircraft Power support

    o   Note this is a change from the previous posted schedule

    o   Please contact Dave F., or Dave J., with specific needs regarding Aircraft Power or Data-IT

-   1300 – 1500 ChST: Aircraft outdoors for additional Payload System Satcom Testing

 

Outlook

-   Tuesday: Preflight activity for Science Teams and  Aircraft Crew (all times ChST):

    o   0900 – 0945: Req’d Engine wash by Crew

    o   1000 – 1300: Instrument Team Pre-flight access with Power

    o   1300 – 1600: Aircraft Preflight

-   The next Science Flight is currently scheduled for Wednesday 22Jan’14

    o   Currently planned Takeoff time: 0600 ChST for a 14 hr flight. 

-   Please contact Dave F., or Dave J., if you have any questions.