Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

2015-02-20

Overview:

  • Instruments and aircraft ready for CST on Monday, Flight on Tuesday
  • Note to all Inst. PI’s – please see GHOC show schedule below

Accomplishments:

  • AFRC “Tech Brief” held – CAST/ATTREX Science Flight Request approved and signed
  • MMS Nav-data cable repaired – tests confirm good data
  • GHOST and AIITS testing
  • Maintenance and avionics pre-flight activity
  • HDVis camera upgraded with new heater film – installed on aircraft
  • AFRC Ku Ground Station reinstalled and will be used during Range Flt.

Issues/Watch items:

  • Previous issues cleared

Upcoming Schedule:
Saturday/Sunday

  • No known activity planned in Payload Cage – no aircraft access

Monday: CST Schedule

  • 0615: GHOST LN2 Fill in the Hangar
  • 0730: T-0 Briefing in Payload Cage
  • 0800: All Instr. P.I.’s required in GHOC
  • CST: ~0815 to ~1100
  • 1300: T-1 Briefing for Range Flt (B4840, Rm 113B)

Tuesday: Range Flight

  • 0400: GHOST LN2 Fill in the Hangar
  • 0500: T-0 Briefing (B4840, Rm 113B)
  • 0550: All Instr. P.I.’s required in GHOC
  • 0600: Engine Start
  • 0700: Take-off

2015-02-19

Overview:

  • Maintenance and Avionics aircraft work continues in preparation for CST
  • CST scheduled – however, all PI’s should look for e-mail at 0800 confirming details

Accomplishments:

  • Maintenance and avionics flight readiness activity continues on aircraft
  • AIITS removed for upload and checkout of new software
  • MMS Nav-data cable modified to reduce noise

Issues/Watch items:

  • Wallops Ku Ground Station pointing issue unresolved
  • Tight schedule Friday regarding final detailed prep

Upcoming Schedule:
Friday

  • Decision on final CST Schedule – PI’s look for Email announcement before coming in
  • 0800 – GHOST and AIITS power-on aircraft testing
  • Data-IT has requested time for outdoor testing in the morning

Saturday

  • Support in Payload Cage for P.I.’s as needed, no aircraft access

2015-02-18

Overview:

  • Pre-CST related activity performed – ready for CST Friday.
  • Air vehicle readiness and instrument integration/testing is on schedule.

Accomplishments:

  • Outdoor Satcom testing, including Pre-CST related testing
  • GHOST Cryostat LN2 fill performed on aircraft outdoors
  • Rehearsal for pre-Engine Start LN2 fill on flight days
  • GHOST TAM alignment measurements performed
  • AIITS troubleshooting software updates

Issues/Watch items:

  • MMS reports some noise on LN-100 nav data line; troubleshoot tomorrow
  • Wallops Ku Ground Station pointing issue unresolved; support from WFF requested

Upcoming Schedule:

Thursday: Maint and Avionics aircraft final prep for CST
Friday: All personnel participate in CST; Schedule TBA
Saturday: Support in Payload Cage for PIs as needed, no aircraft access 

2015-02-17

Overview:

  • MMS and GHOST wiring issues resolved, outdoor Satcom Testing continues tomorrow.
  • Expectation of Pre-CST by COB tomorrow.
  • P.I.’s - see arrival schedule below to support testing and Pre-CST

Accomplishments:

  • NGC reports CAST/ATTREX payload passes shear-bending analysis
  • GHOST Cryostat cool-down and re-installation on aircraft
  • MMS wiring and GHOST IT issues resolved
  • Tech Brief Slide run-through
  • Weekly CAST/ATTREX Leads Telecom

Issues/Watch items:

  • MMS wiring issue required all day to resolve – no outdoor Satcom Testing accomplished today.

Upcoming Schedule:

Wednesday:

  • Crew to stage aircraft at normal Ku-testing location, ready for power at 0730
  • MMS, GHOST, AIITS & Hawkeye: please report to GHOC at 0730
  • O3, NWV, MTP & GWAS: please report to Payload Cage at 0900 (You’ll be called to GHOC as needed by Caitlin)
  • Aircraft outdoor testing all day hopefully concluded with Pre-CST.

Thursday:

  • Maint and Avionics aircraft final prep for CST

Friday:

  • All personnel participate in CST: Schedule TBA

2015-02-13

Overview:

  • All instruments are now integrated on the aircraft
  • Outdoor Satcom Testing has begun

Accomplishments:

  • Outdoor Satcom testing, with Instrument teams in the GHOC has begun
  • NOAA O3 and NWV, MTP, and GWAS complete Iridium testing
  • All four instruments are complete with no testing planned on Tuesday
  • MMS, Hawkeye, AIITS testing has begun 

Issues/Watch items:

  • No Ku Satcom Testing accomplished - the GH Ku Ground Terminal at Wallops was offline (a weather, alignment issue)
  • System needs to be online next Tuesday & Wednesday to stay on schedule
  • Discovered a Data-Ethernet connectivity issue to GHOST, suspected to Payload System based
  • Therefore, Tuesday will begin with additional Hangar IT Testing to troubleshoot
  • Most of Tuesday and all of Wednesday will be used for additional outdoor Satcom testing - to be concluded with the Pre-CST.

Upcoming Schedule:

No P.I. activity in the GH Hangar Sat or Sun or Monday (Holiday). GHOST LN2 Cryo servicing to be performed as scheduled.

Tuesday

  • Begin the morning in the Hangar – troubleshoot GHOST Data-ethernet connectivity issue
  • Aircraft outdoors for Satcom testing when GHOST IT issue resolved
  • Wallops Ku Ground Terminal needed for testing
  • MMS, Hawkeye, AIITS, MTP, GHOST Inst. Teams needed at 0900 (report to Hangar first)
  • NOAA O3, NWV, GWAS, and MTP Team are not needed Tuesday

Wednesday

  • Aircraft outdoors for Satcom Testing, all Inst. Teams needed in GHOC
  • Pre-CST Test, as scheduled.

2015-02-12

Overview:

CAST/ATTREX Instrument integration/testing is on schedule. Wt/Bal completed. Outdoor IT Testing tomorrow.
P.I.’s please see revised show-time schedule below…
 
Accomplishments:

  • AIITS Laser re-installed and instrument is working
  • Hangar Data-IT Testing continued

Upcoming Schedule:

  • Tomorrow, Friday (OA and OM Crew support approved for 8 hours)
    • Begin the morning in the Hangar – finish Data IT Testing
    • Prepare for outdoor Satcom Testing at ~0900.
    • 0730 Show-time for: MMS, GHOST, AIITS
    • 0800 Show-time for: Hawkeye
    • 0900 Show-time for all remaining instruments

2015-02-11

Overview:

CAST/ATTREX Instrument integration/testing on schedule. Aircraft will be ready for Wt/Bal in the morning.
 
Accomplishments:

  • GHOST electrical harnesses installed.
  • Hawkeye harness/fibre end-end test completed
  • Worked MMS Heater EIP Cable
  • AIITS replacement Laser arrived – being installed (non-interference with Wt/Bal)

Concerns / Watch List:

  • Need 2-3 hr of Hangar Data-IT – currently proposed after Wt/Bal tomorrow.
  • NGC Shear/Bending analysis – holding for new NGC analysis using updated model.

Upcoming Schedule:

  • Tomorrow, Thursday:
    • Weight & Balance by NGC Engr. starting at 0800
    • Data-IT Testing in Hangar (GWAS, MMS, Hawkeye, GHOST, AIITS PI’s requested at 1PM to support)
  • Friday
    • All-day Outdoor Satcom/GHOC Testing of Payloads
    • All PI’s requested to support

2015-02-10

Overview:

CAST/ATTREX Instrument integration proceeding as scheduled. GHOST mechanical Installation and AIITS Ping Test completed.
 
Accomplishments:

  • GHOST mechanical installation completed (see pic)
  • AIITS Pod structural dynamics (“Ping”) test completed (see pic)

Concerns / Watch List:

  • AIITS replacement Diode Laser - delivery expected tomorrow.
  • Cannot locate 2nd MMS EIP Harness. OA may need to fabricate a replacement.
  • NGC Shear/Bending analysis – holding for new NGC analysis using updated model.

Upcoming Schedule:

  • Tomorrow, Wednesday:
    • CAST/ATTREX Leads Telecom at 0800 PST
    • Hawkeye Harness end-to-end checks (Zone-3 and Pod)
    • MMS EIP Harness review (Zone-7)
    • GHOST ATR Ping Setup and Test
    • GHOST Harness installation (after Ping Test, time permitting)
  • Thursday:
    • Weight & Balance by NGC Engr.
    • Data-IT Testing in Hangar (time permitting)

2015-02-06

Overview:

  • CAST/ATTREX Instrument integration/test proceeding as scheduled. GHOST Installation has begun in Zone-25 
  • GHOST installation continues Saturday

Accomplishments:

  • AIITS Pod mounting on the wing completed
  • Structural Shear/Bending Analysis review meeting held at NGC
  • Installation of the GHOST Pallet commenced, TAM Mounted and Fairing Cut.

Concerns / Watch List:

  • AIITS Diode Laser replacement has been shipped – expected at AFRC on Monday
  • Reviewing need for laser-replacement waiver
  • NGC Shear/Bending analysis by NGC now suspected to be in error, analysis to be corrected
  • GHOST integration continues Saturday to get on schedule

Upcoming Schedule:

  • Tomorrow, Saturday: GHOST Pallet installation continues
  • Monday:
    • GHOST avionics harness installation
    • Begin Data-IT Hangar Testing of all instruments on aircraft power

2015-02-05

Overview:

CAST/ATTREX Instrument integration proceeding as scheduled. GHOST Installation is 2 days behind schedule… currently the only instrument not mounted.
 
Accomplishments:

  • Cabin Pressurization test completed
  • Avionics tie-up of harnesses ongoing
  • AIITS Pod mounted on the wing, preloads almost completed
  • CAST/ATTREX Leads Status/Flight Planning telecom held
  • Final pre-installation work on the GHOST Pallet continuing

Concerns / Watch List:

  • AIITS Diode Laser replacement arrival by early next week.
  • Need for waiver for replacement of AIITS Laser Module without repeat of Enviro. Testing
  • GHOST Pallet installation is behind schedule – mounting on aircraft to begin tomorrow
  • NGC Shear/Bending analysis - Meeting at NGC tomorrow to discuss status

Upcoming Schedule:

  • Tomorrow, Friday:
    • Finish AIITS Pod load-cell preloads
    • Continue Avionics tie-up of harnesses
    • GHOST Pallet installation
  • Saturday: Finish GHOST Installation