Overview:
CAST/ATTREX Instrument integration proceeding as scheduled. GHOST Z-25 installation is behind schedule due to a delay in pallet prep, however the pallet is expected tomorrow.
Accomplishments:
- All Instruments have passed SIL Bench Testing.
- AIITS Pod completes Environmental Testing
- MMS, MPT, Hawkeye, NWV, O3, and GWAS are mechanically installed.
- AIITS fiber installed – Cabin Pres. Test Thursday AM
Concerns / Watch List:
- AIITS Diode Laser replacement arrival by early next week.
- Need for waiver for replacement of AIITS Laser Module without repeat of Enviro. Testing
- GHOST Pallet installation is behind schedule – expected to begin tomorrow
- NGC Shear/Bending analysis - Meeting at NGC on Friday to discuss status
Upcoming Schedule:
- Tomorrow, Thursday:
- 0800 CAST/ATTREX Proj. Lead Telecom
- Cabin Pressurization Test
- Continue Avionics tie-up of harnesses
- AIITS Pod Installation
- GHOST Pallet installation
- Friday / Saturday:
- Finish GHOST Installation
- Aircraft Wt. & Balance (day/time TBD)