Monday, March 26 Accomplishments
  • CIT-CIMS rack installed and cabled
  • NOAA CIMS cylinders loaded onto aircraft, exhaust line and inlet installed, rack powered and checked out in lab
  • GT-CIMS cylinders loaded onto aircraft, prepping rack in lab
  • MMS troubleshooting software
Tuesday, March 27 Plan
  • 06:00 - 17:30: A/C Access
  • CIT-CIMS pump installation
  • NOAA CIMS rack upload

Thursday, 3/22 Accomplishments
  • AO2/Medusa continued optimizing
  • CAPS team departs
  • GT-CIMS power up in lab
  • HR-AMS calibrations and software
  • ISAF completed installation
  • Sea shipment departed for Christchurch
  • Cylinder shipment departed for Anchorage, Kona and Lajes
Friday, 3/23 Plans
  • AO2/Medusa team departs
  • GT-CIMS lab work
  • HR-AMS team departs
  • ISAF team departs

Wednesday, 3/21 Accomplishments
A02/Medusa mach flight
CAPS completed on a/c work, removed & stowed instrument in lab, packed
GT-CIMS installed exhaust line
HR-AMS leak checks and calibrations
ISAF finishing cabling and plumbing, power check either today or tomorrow

Thursday, 3/22 Plans
Egress training at 13:30
A02/Medusa continue optimization
CAPS departs (returns 4/8)
GT-CIMS power up in lab
HR-AMS calibrations
ISAF

Friday, 3/23 RDO
Lab access, no A/C access

Monday, 3/26
A/C access 10:00-17:30 (engine run a.m.)

Tuesday, 3/20 Accomplishments
AO2/Medusa finished installed plumbing and powered up
CAPS cross computer calibrations and systems checks
GT-CIMS staged shipping material and began to unpack
HR-AMS installed and conducted power checks and alignment
ISAF completed mechanical installation and began cabling
Shipment preparations

Wednesday, 3/21 Plans
A/C access 16:00-17:30
A02/Medusa continue checks and optimize
CAPS continue system checks & pack
GT-CIMS instrument lab check-outs
HR-AMS calibrations 
ISAF complete cabling and plumbing and finish installation
Shipment preparations continue

Monday, 3/19 Accomplishments
AO2/Medusa, ISAF and HR-AMS arrived
AO2/Medusa installed and powered on
ISAF installed
HR-AMS calibrating in lab

Tuesday, 3/20 Plans
06:00-17:30    A/C access
HR-AMS planning to install

Monday, 3/19 Plan
07:00    Badge office opens (for those with expired badges)
06:00-18:00    A/C access    
CAPS installation continues
AO2/Medusa, HR-AMS, ISAF teams begin installations

Friday, 3/16 Accomplishments
All first round instruments installed
No NOyO3 issues
CAPS installation complete

Weekend lab access but no A/C access

Monday, 19 Plan
ISAF, AO2/Medusa & HR-AMS begin installations

Thursday, 3/15 Accomplishments
AMP, ATHOS, QCLS, MMS, TOGA, CAFS, DLH, PALMS, Picarro, SAGA and SP2 completed installations
NOyO3 installed, working pump issue
SOAP installed, conducted power checks then removed for shipping to DEN tonight
S02 installed, conducted power checks, a couple issues remain to be resolved
CAPS installation ongoing
Egress training

Friday, 3/16 Plan
06:00-16:30    A/C access
PANTHER/UCATS power checks 
NOyO3 continue working pump issue and calibrations

Wednesday, 3/14 Accomplishments
ATHOS, AMP, CAFS, DLH, MMS, NOyO3, PALMS, Picarro, QCLS, SAGA and TOGA installed
Power checks ongoing (QCLS, Picarro and DLH complete)
CAPS team arrived

Thursday, 3/15 Plan
Continue installations and power checks

All ATom-4 Deployment Guides now available on website:
https://espo.nasa.gov/atom/deployment_guides

Tuesday, 3/13 Accomplishments
NOyO3, QCLS, DLH, Picarro, TOGA, MMS, ATHOS, SAGA and CAFS mechanically installed

Wednesday, 3/14 Plan
NO on the plane in the forward pit
Check with crew prior to first boarding A/C

06:00-17:00 A/C access
Install PALMS, AMP and PANTHER/UCATS rack
Power checks