ATTREX 02/07/14 Daily Schedule

ATTREX  GH Overview:

- After the scrub today, instruments needing off-aircraft testing were removed

- OmniSTAR testing and consultation with NGC and USAF continues.

- Bernie Luna will assume responsibility as onsite ATTREX Proj. Mgr starting tomorrow.

 

Today’s Activities:

- Science Flight scrubbed due to OmniSTAR issues on the aircraft

- OmniSTAR Testing is being performed this afternoon on a USAF GH for comparison info

- AV-6 outdoor OmniSTAR testing continues this evening

  o All aircraft panels and Z-25 Fairing to be secured on aircraft in case of rain while outdoors

 

The Plan for tomorrow (Saturday) is:

- 0700: Normal “0730” daily morning meeting of Leads for GH, ESPO, Science in the Hangar

- All-hands Science Team Mtg – see Eric’s e-mail. Tentative time: 0830, (Conf. Rm., Building 18006, Rm 15)

- Note: Due to the option of more outdoor OmniSTAR testing, aircraft access is likely very limited for instrument teams.

  o Anyone needing access, please contact Dave F. so we can plan for it.

 

Outlook:

- A replacement  NASA GH OmniSTAR unit will arrive in Guam tomorrow night.

  o After installation, aircraft outdoor testing will occur.

- The next flight date will be set once the OmniSTAR issue is resolved.