Overview:
AV-1 Ready for CST – Science Team’s on scheduled break from AFRC/WFF
AV-6 Integ.
Overview:
AV-1 Ready for CST – Science Team’s on scheduled break from AFRC/WFF
AV-6 Integ.
Overview:
AV-1 Integration/Test completed on schedule – ready for CST-prep on 11Aug
AV-6 Integ. on schedule – Outdoor Satcom testing w/WFF starts Monday
Today’s Accomplishments:
AV-1 Science Integ/Test activity ends
o HIWRAP data-file download
o Aircraft jacked for gear maint. (pic)
o Science Flight-prep starts: Monday, 11Aug (see below note)
AV-6 Wt & Balance
o CPL power harness expanded to EIP-4
Overview:
AV-1 and AV-6 integration and testing is on schedule.
Today’s Accomplishments:
AV-1 HIRAD RF Test complete
o HIWRAP waveform refinement activity
o HIRAD & HAMSR removal for camera work & A/C maint.
AV-6 Hangar IT Testing
o AVAPS Testing complete
o S-HIS Testing complete
o CPL Installed and Testing in work
H.S. Student visit
The Plan for Friday (all times PDT):
Overview:
AV-1 and AV-6 integration and testing is on schedule.
Today’s Accomplishments:
AV-1 passed Pre-CST
AV-6 integration activity started
o S-HIS – ready for Hangar IT Testing
o AVAPS – Installation complete, function testing complete
o CPL – SIL Bench completed, Zone-7 installed
§ Zone-3 installation ready (holding for camera work in area)
Japanese Film Crew for HS3 visits GH Hangar
The Hurricane Imaging Radiometer, known as HIRAD, will fly aboard one of two unmanned Global Hawk aircraft during NASA's Hurricane Severe Storm Sentinel or HS3 mission from Wallops beginning August 26 through September 29.
Overview:
AV-1 Testing on schedule
AV-6 Integration continues
Today’s Accomplishments:
AV-1 Outdoor testing with GHOC-E participation (pic)
o HAMSR - complete
o HIRAD – complete
o HIWRAP – complete
AV-6 integration activity started
o S-HIS – installed (pic)
o AVAPS – installed (pic)
o CPL – SIL Bench in work
Overview:
AV-1 Testing on schedule
AV-6 Integration has begun
Today’s Accomplishments:
AV-1 Outdoor testing with GHOC-E participation
o HAMSR - complete
o HIRAD – continues tomorrow
o HIWRAP repaired today – testing tomorrow
AV-6 integration activity started
o S-HIS – SIL Bench Complete
o AVAPS – SIL Bench in work
o CPL – expected tomorrow
AFRC Overview:
AV-1 Integration and aircraft activity continue
AFRC Accomplishments:
Avionics prepped for power
Power to instruments
Hangar IT testing
HAMSR and HIRAD successfully powered and transferred data. HIWRAP successfully powered and is troubleshooting an optical connection.
AFRC Outlook:
No activity planned for Saturday or Sunday
Monday 0830: AV-1 Outdoor Satcom/GHOC-E Data-IT testing of Instruments
Monday: AV-6 S-HIS and AVAPS Teams arrive, Integration activity
Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.