Overview:
AV-1 and AV-6 integration and testing is on schedule.
Today’s Accomplishments:
AV-1 passed Pre-CST
AV-6 integration activity started
o S-HIS – ready for Hangar IT Testing
o AVAPS – Installation complete, function testing complete
o CPL – SIL Bench completed, Zone-7 installed
§ Zone-3 installation ready (holding for camera work in area)
Japanese Film Crew for HS3 visits GH Hangar
The Plan for Thursday (all times PDT):
AV-1 HIRAD RF Test:
o 0645 Pretest Tag-up
o 0700 - 0900 Test
AV-1 Deintegration of HIRAD and HAMSR
o To support next week’s Camera Daylight Cam work & Gear Maint
AV-6 Hangar IT Testing:
o 0700: Daylight Cam installation
o 0800: CPL Zone-3 Installation
o 0900 - ?: Hangar IT Testing
1000: COMSEC WFF (by VITS) Briefing for AFRC personnel
The Plan for Friday:
AV-1: Data-IT work with Cameras (Fratello)
o No PI activity scheduled
AV-6: Wt/Balance
o No PI activity scheduled
Outlook:
No Sat/Sun activity scheduled
Monday @ AFRC: AV-6 Outdoor Testing
o Schedule TBD (PI’s should be present starting at 0830)
Monday @ WFF:
o 0730: Badging, if needed
o 0800: Scan Laptops
o 0930: COMSEC Briefing
o 1000 – 1100: Software Downloads/installs, if required
o 1100 – 1130: Eat Lunch
o 1130: Begin Satcom Testing in GHOC-E