HS3 07/23/14 Daily Schedule

Overview:

AV-1 and AV-6 integration and testing is on schedule.

 

Today’s Accomplishments:

AV-1 passed Pre-CST

AV-6 integration activity started

o   S-HIS – ready for Hangar IT Testing

o   AVAPS – Installation complete, function testing complete

o   CPL – SIL Bench completed, Zone-7 installed

§  Zone-3 installation ready (holding for camera work in area)

Japanese Film Crew for HS3 visits GH Hangar

The Plan for Thursday (all times PDT):

AV-1 HIRAD RF Test:

o   0645 Pretest Tag-up

o   0700 - 0900 Test

AV-1 Deintegration of HIRAD and HAMSR

o   To support next week’s Camera Daylight Cam work & Gear Maint

AV-6 Hangar IT Testing:

o   0700: Daylight Cam installation

o   0800: CPL Zone-3 Installation

o   0900 - ?: Hangar IT Testing

1000: COMSEC WFF (by VITS) Briefing for AFRC personnel

 

The Plan for Friday:

AV-1: Data-IT work with Cameras (Fratello)

o   No PI activity scheduled

AV-6: Wt/Balance

o   No PI activity scheduled

 

Outlook:

No Sat/Sun activity scheduled

Monday @ AFRC: AV-6 Outdoor Testing

o   Schedule TBD (PI’s should be present starting at 0830)

Monday @ WFF:

o   0730: Badging, if needed

o   0800: Scan Laptops

o   0930: COMSEC Briefing

o   1000 – 1100: Software Downloads/installs, if required

o   1100 – 1130: Eat Lunch

o   1130: Begin Satcom Testing in GHOC-E

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.