Overview:
AV-1 Testing on schedule
AV-6 Integration has begun
Today’s Accomplishments:
AV-1 Outdoor testing with GHOC-E participation
o HAMSR - complete
o HIRAD – continues tomorrow
o HIWRAP repaired today – testing tomorrow
AV-6 integration activity started
o S-HIS – SIL Bench Complete
o AVAPS – SIL Bench in work
o CPL – expected tomorrow
The Plan for Tuesday is (all times PDT):
0730: Payload Cage meeting of Leads and PI’s
0800: AV-1 Aircraft taken outdoors
0830 (1130 EDT): Testing & GHOC-E Support begins in this order:
o HIWRAP
o HIRAD
o Facility Instruments
Installation of S-HIS and AVAPS in AV-6
The Plan for Wednesday is:
AV-1 Outdoor Testing to continue as needed
AV-6 Integration of CPL
Outlook:
AFRC:
o Thursday: AV-1 Pre-CST (Possible HIRAD Test), AV-6 Hangar IT
o Friday: AV-1 HIRAD Testing, AV-6 Wt/Bal
WFF:
o Thursday: Support AV-1 Pre-CST (possible HIRAD Testing)
o Friday: Support HIRAD Testing