HS3 07/21/14 Daily Schedule

Overview:

AV-1 Testing on schedule

AV-6 Integration has begun

 

Today’s Accomplishments:

AV-1 Outdoor testing with GHOC-E participation

o   HAMSR - complete

o   HIRAD – continues tomorrow

o   HIWRAP repaired today – testing tomorrow

AV-6 integration activity started

o   S-HIS – SIL Bench Complete

o   AVAPS – SIL Bench in work

o   CPL – expected tomorrow

The Plan for Tuesday is (all times PDT):

0730: Payload Cage meeting of Leads and PI’s

0800: AV-1 Aircraft taken outdoors

0830 (1130 EDT): Testing & GHOC-E Support begins in this order:

o   HIWRAP

o   HIRAD

o   Facility Instruments

Installation of S-HIS and AVAPS in AV-6

 

The Plan for Wednesday is:

AV-1 Outdoor Testing to continue as needed

AV-6 Integration of CPL

 

Outlook:

AFRC:

o   Thursday: AV-1 Pre-CST (Possible HIRAD Test), AV-6 Hangar IT

o   Friday: AV-1 HIRAD Testing, AV-6 Wt/Bal

WFF:

o   Thursday: Support AV-1 Pre-CST (possible HIRAD Testing)

o   Friday: Support HIRAD Testing

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.