Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

Associated content: 
Sub-categories: 

HS3 08/26/14 Daily Schedule

Overview:  AV-6 arrives WFF Wed following transit/Hurricane Cristobal collection. Plan is to fly AV-6 again Thur targeting Hurricane Cristobal.  Troubleshooting continues on AV-1.

 

HS3 08/25/14 Daily Schedule

Overview:  AV-6 transit to WFF Tue-Wed.  Troubleshooting continues on AV-1.

 

HS3 08/24/14 Daily Schedule

Overview - repair is completed on AV-6 and pre-flights will occur Monday. Troubleshooting will continue Monday on AV-1.
 
Monday August 25
WFF (EDT)
     -     0800 Forecast Briefing S115

HS3 08/23/14 Daily Schedule

Overview - both jets are undergoing repair/troubleshooting.
 
The goal is a takeoff Tuesday morning at 0600 PDT, likely AV-6.

Sunday August 24

Fair Weather Cumulus_BW

HS3 08/22/14 Daily Schedule

Overview - both jets are undergoing repair/troubleshooting.

The goal is a takeoff Tuesday morning, and a takeoff Wednesday morning, each 22 hours duration with science. The order of transits (AV-1 or AV-6) has not been determined.

HS3 08/21/14 Daily Schedule

Overview - today's flight is on but with AV-1 not AV-6

-     AV-1 Transit Flight tonight
-     AV-6 Transit Flight possible tomorrow night   

TONIGHT - Aug 21, 2014: AV-1 Transit
-     AFRC (PDT):
           1700 Engine Start
           1800 Takeoff

-     WFF (EDT):
           1930 Staff GHOCE for AV-1 Transit
           2000 Engine Start
           2100 Takeoff

HS3 08/20/14 Daily Schedule

Overview
-     AV-1 Transit Flight tonight
-     AV-6 Transit Flight tomorrow night
 
Today's Accomplishments:
-     AV-6 Fuel and Pre-flight

D-1 Hangar ready for AV-1