A new Doppler radar takes flight on this summer's HS3 mission.
HS3
DFRC UPDATE:
AV-1 Completed:
Pending: new camera lens for nose camera
AV-1 Goals:
Friday August 2 - Power on for HIWRAP, time approximately 1000
Monday August 5 - pre-CST; PI's arrive 0800 in hangar. Comsec training ~1300
AV-6 Completed:
Thursday August 1 - Range flight
AV-6 Goals:
Friday August 2 - instrument access 0800-1000; prepare crates for shipping 1000-1100
WFF UPDATE:
AV-1 Goals:
Monday August 5
1000 PIs check in with ESPO
1030 PI's in GHOC-E
DFRC UPDATE:
AV-1 Completed:
Pending: new camera lens for nose camera
AV-6 Completed:
Wednesday July 31 - instrument pre-flight and aircraft pre-flight; AVAPS RF troubleshooting
AV-6 Goals:
Thursday August 1 - Range flight
0630 takeoff
1230 estimated landing
Friday August 2 - instrument access 0800
WFF UPDATE:
AV-6 Completed:
Wednesday July 31 – 0930 COMSEC Brief (for new arrivals)
AV-6 Goals:
0800 PIs at stations in GHOC-E
Thursday August 1 - Range flight
DFRC UPDATE:
AV-1 Completed:
Pending: new camera lens for nose camera
AV-6 Completed:
Tuesday July 30 – CST, aircraft testing
AV-6 Goals:
Wednesday July 31 - instrument pre-flight and aircraft pre-flight; PI access 0800-1000
Thursday August 1 - Range flight
0630 takeoff
1230 estimated landing
Friday August 2 - instrument access
WFF UPDATE:
AV-6 Completed:
Tuesday July 30 – CST
DFRC UPDATE:
AV-1 Completed:
Pending: new camera lens for nose camera
AV-6 Completed:
Monday July 29 - pre-CST
AV-6 Goals:
Tuesday July 30 – CST, engine start 0700, no PI's required
Wednesday July 31 - instrument pre-flight and aircraft pre-flight
Thursday August 1 - Range flight, 0630 takeoff
WFF UPDATE:
AV-6 Completed:
Monday July 29 - pre-CST
DFRC UPDATE:
AV-1 Completed:
Pending: new camera lens for nose camera
AV-6 Completed:
Friday July 26 - In-hangar IT/comm troubleshooting
AV-6 Planned:
Saturday - no PI activities
Sunday - no PI activities
Monday - pre-CST PI's arrive 0700 PDT
WFF UPDATE:
AV-6 Completed:
Friday July 26 - IT/Comm testing
AV-6 Planned:
Saturday - no PI activities
Sunday - no PI activities
Monday - pre-CST PI's arrive 1000 EDT
DFRC UPDATE:
AV-1 Completed:
Thursday July 25 - removed EIPs 1/6 for firmware update
Pending: new camera lens for nose camera, EIP firmware
AV-6 Completed:
Thursday July 25 - Outdoor Payload-IT testing and in-hangar troubleshooting
AV-6 Goals:
Friday July 26 – IT/Comm troubleshooting, 0600-1430 (no PI's needed)
Saturday - no PI activities
Sunday - no PI activities
Monday - pre-CST PI's arrive 0700 PDT
DFRC UPDATE:
AV-1 Completed:
HIWRAP Battery switch
Pending: new camera lens for nose camera.
AV-6 Completed:
Wednesday July 24 - Outdoor Payload-IT testing
Goals:
Thursday July 25 – Continue Outdoor Payload-IT testing, 0600-1430 (PIs needed at 0700)
WFF UPDATE
AV-6 Completed:
Wednesday July 24 - Outdoor Payload-IT testing
AV-6 Goals:
Thursday July 25 - Continue Outdoor Payload-IT testing, 1000-1730
DFRC UPDATE:
AV-1
Pending: HIWRAP Battery switch, new camera lens for nose camera.
AV-6 Completed:
Tuesday July 23 - Initial Outdoor Payload-IT testing.
Goals:
Wednesday July 24 – Continue Outdoor Payload-IT testing, 0600-1430 (PIs needed at 0700)
WFF UPDATE
AV-6 Completed:
Tuesday July 23 - COMSEC Brief 0900, Initial Outdoor Payload-IT testing.
AV-6 Goals:
Wednesday July 24 - Continue Outdoor Payload-IT testing, 1000-1730
DFRC UPDATE:
AV-1 Completed:
Monday July 22 - Outside testing for Ku comms and intercoms.
Goals:
Pending: HIWRAP Battery switch, new camera lens for nose camera.
AV-6 Completed:
Monday July 22 – Wt & Balance and fueling
Goals:
Tuesday July 23 - Initial Outdoor Payload-IT testing, 0600-1430 (PIs needed at 0800)
Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.