HS3 08/15/13 Daily Schedule

Dry Run continues daily through 08/16 (this Friday) at 0800 PDT/1100 EDT

On Saturday we commence regular Forecast briefings at 0830 and 2030 EDT

 

DFRC UPDATE (PDT):

AV-6 Goals:

Thursday Aug 15:

AV-6 Ferry

1700 Engine Start

1800 Take Off

Shipping - Coordinate with Dave Jordan on details

Friday August 16: truck shipment departs

 

WFF UPDATE (EDT):

AV-6 Goals:

Thursday Aug 15:

AV-6 Ferry

1930  PIs take places in GHOC – E

2000 Engine Start

HS3 08/14/13 Daily Schedule

Dry Run continues daily through 08/16 (this Friday) at 0800 PDT/1100 EDT

On Saturday we commence regular Forecast briefings at 0830 and 2030 EDT

 

DFRC UPDATE (PDT):

AV-6 Goals:

Pending: Nose camera lens installation and checkout

Thursday Aug 15:

AV-6 Ferry

1700 Engine Start

1800 Take Off

Shipping - Coordinate with Dave Jordan on details

Friday August 16: truck shipment departs

 

WFF UPDATE (EDT):

AV-6 Goals:

Pending: Nose camera lens installation and checkout

HS3 08/13/13 Daily Schedule

Dry Run continues daily through 08/16 (this Friday) at 0800 PDT/1100 EDT

 

DFRC UPDATE (PDT):

AV-6 Goals:

Pending: Nose camera lens installation and checkout

AV-1 Goals:

Tuesday Aug 13:  AV-1 Ferry

1700 Engine Start

1800 Take Off

Wednesday Aug 14:

AV6 Instrument Access for preflight (1000-1300)

Aircraft preflight

AV-1 PI's coordinate shipping details with Dave Jordan by noon Wednesday

Thursday Aug 15:  truck staging and AV-6 Ferry

1700 Engine Start

HS3 08/12/13 Daily Schedule

Dry Run continues daily until 08/16 at 0800 PDT/1100 EDT

 

DFRC UPDATE (PDT):

AV-6 Goals:

Pending: Nose camera lens installation and checkout

AV-1 Goals:

Monday Aug 12:

AV1 Instrument Access for preflight (1000-1300)

AV-1 Aircraft preflight

Tuesday Aug 13:  AV-1 Ferry

1800 Engine Start

1900 Take Off

Wednesday Aug 14:

AV6 Instrument Access for preflight (1000-1300)

Aircraft preflight

Thursday Aug 15:  AV-6 Ferry

1800 Engine Start

HS3 08/09/13 Daily Schedule

A quote from an instrument team member late for a deadline…."My biggest mistake was not reading the POD."

 

DFRC UPDATE:

AV-6 Goals:

Pending: Nose camera lens installation and checkout

AV-1 Completed:

Friday Aug 9:  Instrument Postflight

AV-1 Goals:

Saturday Aug 10:  No PI activities

Sunday Aug 11:  Hard down Day

TENTATIVE PLAN FOR NEXT WEEK

Monday Aug 12:

AV1 Instrument Access for preflight (1000-1300)

AV-1 Aircraft preflight

HS3 08/08/13 Daily Schedule

DFRC UPDATE:

AV-6 Goals:

Pending: Nose camera lens installation and checkout

AV-1 Completed:

Instrument Range Flight

AV-1 Goals:

Pending: Nose camera lens installation and checkout

Friday Aug 9:  Instrument Access for Postflight and, if desired, ferry

post/preflight (1000-1400)

Possible PI shipment to WFF. Contact Dave Jordan in hangar 4840, extension 2050.

Saturday Aug 10:  No PI activities.

Sunday Aug 11:  Hard down Day

HS3 08/07/13 Daily Schedule

Forecast Dry Run; August 6-16; See email sent to list serve on 7/30/13, titled 'HS3 Dry Run 2013'.

Please Note: Transits next week  are planned for takeoff at ~7 pm PDT; land ~0800 EDT. There is a possibility of a longer flight due to weather, science goals, or range conflicts. Please plan accordingly. See GHOC and GHOC-E Instrument Team Staffing notes below.

DFRC UPDATE:
AV-6 Goals:

Pending: Nose camera lens installation and checkout

AV-1 Completed:

Instrument Post/Pre-flight and Aircraft Preflight

HS3 08/06/13 Daily Schedule
DFRC UPDATE:
AV-6 Goals:

Pending: Nose camera lens update

AV-1 Completed:

CST

AV-1 Goals:

Pending: Nose camera lens update

Wednesday August 7;  Instrument pre-flight and aircraft pre-flight

PI access 0800-1000 PDT

Thursday August 8;   Range Flight

PIs not required

Engine start 0600

Take off 0700

Landing 1200

Friday August 9: shipment prep

WFF UPDATE:
AV-1 Completed:

CST

AV-1 Goals:

Thursday August 8;   Range Flight

HS3 08/05/13 Daily Schedule
DFRC UPDATE:
AV-6 Completed:

fueled

AV-1 Completed:

pre-CST

AV-1 Goals:

Pending: Nose camera lens update

Tuesday, August 6: CST; PI's optional, arrive 1100 in hangar. 1130 engine start

(delayed start due to airfield conflict)

Wednesday August 7: instrument pre-flight and aircraft pre-flight

Thursday August 8: range flight

Friday August 9: shipment (begin to think about this)

WFF UPDATE:
AV-1 Completed:

pre-CST

AV-1 Goals:

Tuesday August 6 - CST 1430

HS3 08/02/13 Daily Schedule
DFRC UPDATE:
AV-1 Completed:

HIWRAP software update

ADELE re-installed

2 trucks loaded

AV-1 Goals:

Pending: Nose camera lens update

Monday August 5 - pre-CST; PI's arrive 0800 in hangar. Comsec training ~1300

AV-6 Completed:

Friday August 2 - instrument post-flight; SHIS/AVAPS crates to DFRC shipping

WFF UPDATE:
AV-1 Goals:

Monday August 5 - pre-CST 1100

1000 PIs check in with ESPO

1030 PI's in GHOC-E

1100 pre-CST

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.