DFRC UPDATE:
AV-1 Completed:

Pending:  new camera lens for nose camera

AV-6 Completed:

Friday July 26 - In-hangar IT/comm troubleshooting

AV-6 Planned:

Saturday - no PI activities

Sunday - no PI activities

Monday - pre-CST PI's arrive 0700 PDT

WFF UPDATE:
AV-6 Completed:

Friday July 26 - IT/Comm testing

AV-6 Planned:

Saturday - no PI activities

Sunday - no PI activities

Monday - pre-CST PI's arrive 1000 EDT

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.