HS3 07/20/13 Daily Schedule
DFRC UPDATE:
AV-1
Goals:

Monday July 22 - Outside testing for Ku comms and Cronus checkout, 0600-1430 (no PIs needed)

Pending:   HIWRAP Battery switch, new camera lens for nose camera.

AV-6 Completed:

Saturday July 20 – CPL and AVAP powered in hangar.

Goals:

Sunday July 21 – HARD DOWN DAY

Monday July 22 – Wt & Balance and fueling

Tuesday July 23 - Initial Outdoor Payload-IT testing, 0800-1430

HS3 07/19/13 Daily Schedule
DFRC UPDATE:
AV-1 Completed:

Friday July 19 – PI Instrument backbone test.

Goals:

Friday July 19 – Indoor power-on testing in afternoon

Saturday July 20  – PIs travel home.  Return Aug 4.  Ops begin Aug 5.

Sunday July 21 – HARD DOWN DAY

Monday July 22 - Outside testing for Ku comms and Cronus checkout, 0600-1430 (no PIs needed)

Pending:   HIWRAP Battery switch, new camera lens for nose camera.

AV-6 Completed:

Friday July 19 – Final integration.

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.