HS3 07/19/13 Daily Schedule

DFRC UPDATE:
AV-1 Completed:

Friday July 19 – PI Instrument backbone test.

Goals:

Friday July 19 – Indoor power-on testing in afternoon

Saturday July 20  – PIs travel home.  Return Aug 4.  Ops begin Aug 5.

Sunday July 21 – HARD DOWN DAY

Monday July 22 - Outside testing for Ku comms and Cronus checkout, 0600-1430 (no PIs needed)

Pending:   HIWRAP Battery switch, new camera lens for nose camera.

AV-6 Completed:

Friday July 19 – Final integration.

Goals:

Saturday July 20  – Power-on inside the hangar 0700-1200

Sunday July 21 – HARD DOWN DAY

Monday July 22 – Wt & Balance and fueling

Tuesday July 23 - Initial Outdoor Payload-IT testing, 0800-1430

The Ku system at Wallops will be used for the testing on Monday and Tuesday.
WFF UPDATE:
AV-1 Completed:

Friday July 19 – PI Instrument backbone.

Goals:

Saturday July 20  – PIs travel home.  Return Aug 4.  Ops begin Aug 5.

AV-6 Goals:

Sunday July 21 -  PIs travel.  Prep begins July 22

Monday July 22 – Wt & Balance and fueling; PIs set up / computer scans etc.

Tuesday July 23 -  Initial Outdoor Payload-IT testing, 1100-1730

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.