Saturday, 5/25 Accomplishments:
General instrument integration work continued
Sunday & Monday (5/26 & 5/27):
Lab access, no A/C access
Saturday, 5/25 Accomplishments:
General instrument integration work continued
Sunday & Monday (5/26 & 5/27):
Lab access, no A/C access
Friday, 5/24 Accomplishments:
PTR-MS and CARE, CAFS, LARGE and mini-DOAS shared rack installed on A/C
mini-DOAS instrument removed from rack for lab work
LINEPH on A/C; mechanical installation awaits mounting plate (~6/9)
At the end of the week we’ve got: NOyO3, CAFS, DLH/DACOM, AOP, SAGA,
the LARGE, CAFS, CARE, mini-DOAS and AS-TEM shared rack and PTR-MS installed.
Saturday, 5/25 Plan:
07:00 A/C access
General instrument integration work continues
15:00 A/C access ends
Sunday & Monday (5/26 & 5/27):
Lab access, no A/C access
Thursday, 6/23 Accomplishments
Continuation of instrument on A/C integration tasks
LARGE passed tipping moment requirement and is on A/C
PTR-MS instrument arrived, was unpacked and prepped for upload
MASTER prep work continues for instrument arrival on 6/3
Successfully navigated Foreign National escort audit
Friday, 6/24 Plan
06:00 A/C access
Continuation of instrument on A/C integration tasks
Upload PTR-MS
Upload CARE, CAFS, mini-DOAS and LARGE shared rack
Determine Saturday A/C access requirements
17:30 A/C access ends
Wednesday, 6/22 Accomplishments
AOP physically installed
Instrument installation work continued
Working on getting power to racks
LARGE instrument reconfiguring rack to satisfy overturning moment
Thursday, 6/23 Plan
06:00 A/C access
Instrument installation work continues
Mini-DOAS team arrives
17:30 A/C access ends
Tuesday, 6/21 Accomplishments
DIAL, LARGE, NOyO3, SAGA, CAFS and MASTER installation work continues
NOyO3 overtuning moment test completed on aircraft
AOP and CARE working in lab
Wednesday, 6/22 Plans
06:00 A/C access
Continue instrument installation work
AOP upload
NOyO3 hazardous gas on a/c
17:30 A/C access ends
Send pressure system schematics to Richard Wong and have him inspect your pressure systems.
Don’t forget to secure all gas cylinders; on a/c and elsewhere.
Monday, 5/20 Accomplishments
NOAA and LaRC trucks unloaded
Some obtained badges
NOyO3 and DACOM racks on A/C
Praxair order arrived
Tuesday, 5/21, Plan
06:00 A/C access
07:00 Continue badging efforts
13:00 Meeting in Lab
(Foreign Nationals and Escorts meeting after 13:00 meeting)
17:30 A/C access ends
Due to reduced staff A/C support after 15:00 will be minimal if at all.
Alert A/C crew if hazardous material is being taken onto A/C
Monday, 6/20
06:00 A/C access
07:00 Visitor Control Center (VCC) opens
08:00 NOAA Truck arrives
Monday, 6/20
06:00 A/C access
07:00 Visitor Control Center (VCC) opens
08:00 NOAA Truck arrives
Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.