2019-06-05

Wednesday, 6/5, Accomplishments:
OPALS team performed in lab installation prep
mini DOAS team performed in lab calibrations
ACES and IWAS testing in lab, waiting for the install window
TOGA installed
ISAF/ROZE/CANOE and SO2/NO-LIF installed
CIT-CIMS rack and pump plate installed
DIAL completed nadir alignments

Thursday, 6/6, Plans:
06:00 A/C Access
IWAS/ACES install
Instrument installations and integration
13:00 Lab meeting
17:30 A/C access ends

Tools taken from community A/C tool box must be returned at the end of the day
Label gas bottles
Empty gas bottles need to be in the empty bottle area on the back side of building 716
Send pressure system schematics to Richard Wong
Send heater system schematics to Paul Martinez/Brennan Wehr

2019-06-04

Tuesday, 6/4, Accomplishments:
UCLA WAS kicked off project
UCI WAS installed
IWAS rack satisfied over-turning moment on 2nd attempt
UCI WAS, TOGA and MMS installed
NOAA LGR/PTR-ToF-MS rack on A/C
ISAF, SO2 (NO-LIF) rack prepped for install
CIT-CIMS rack prepped for install 
mini-DOAS prepped for install (rack already on A/C)

Wednesday, 6/5, Plans:
06:00 A/C Access
Instrument installations and integration
13:00 Lab meeting
17:30 A/C access ends

Label gas bottles
Empty gas bottles need to be in the empty bottle area on the back side of building 716
Send pressure system schematics to Richard Wong
Send heater system schematics to Paul Martinez/Brennan Wehr

2019-06-03

Monday, 6/3, Accomplishments:
ISAF (ROZE & CANOE), WAS, NOAA LGR, PTR-ToF-MS, SO2 (NO-LIF), iWAS, ACES, and MASTER instruments and teams arrived
WAS rack installed
GT-CIMS on A/C power check
On A/C integration work continued for PTR-MS and HR-AMS2
CARE crew worked in lab and formulated a plan to deal with circuit board issue

Tuesday, 6/4, Plans:
06:00    A/C Access
Instrument installations and integration
13:00    Lab meeting
13:30    Egress training
17:30    A/C access ends

Label all compressed gas bottles
Empty gas bottles need to be in the empty bottle area on the back side of building 716
Send pressure system schematics to Richard Wong
Send heater system schematics to Paul Martinez/Brennan Wehr

2019-06-02

Sunday, 6/2, Accomplishments:
CARE team worked in lab and packed for departure

Monday, 6/3 Plans:
06:00    A/C access
07:00     Visitor Control Center (VCC, Badge office) opens
13:00    Meeting in lab
17:30    A/C access ends

Those without NASA badges will need to obtain a badge (VCC)
Those with other than AFRC NASA badges will need to obtain a PIN for building 703 access (VCC)
Those that have satisfied Foreign National Escort requirements will get a FN Escort specific badge later in the day.

2019-06-01

Saturday, 6/2, Accomplishments:
Continuation of A/C integration work
CARE received circuit board but still has a problem

Sunday, 6/3, Plans:
No A/C access
07:30    Lab access
15:00    Lab access ends

2019-05-31

Friday, 5/31 Accomplishments:
SP2 completed integration
CAMS, DLH/DACOM, HR-AMS2, GT-CIMS and PTR-MS continued A/C integration

Saturday, 6/1 Plans:
07:00 A/C access
CARE to receive new circuit board and begin replacement/checkout
15:00 A/C access ends

Be sure to secure all gas cylinders on/off A/C
ESPO procured cylinder storage moved to conex box 
Send pressure system schematics to Richard Wong
Send heater system schematics to Brennan Wehr/Paul Martinez

2019-05-30

Thursday, 5/30 Accomplishments:
CAMS, CARE, DLH/DACOM, Iodide CIMS, LARGE, PTR-MS and SP2 continued on A/C integration
HR-AMS and GT-CIMS installed

Friday, 5/31 Plans:
07:00 A/C access
On A/C Integration work to continue
13:00 Lab meeting
15:00 A/C access ends

Be sure to secure all gas cylinders on/off A/C
ESPO procured cylinder storage moved to conex box 
Send pressure system schematics to Richard Wong
Send heater system schematics to Brennan Wehr/Paul Martinez

2019-05-29

Wednesday, 5/29 Accomplishments:
CARE, DLH/DACOM and LARGE continued on A/C integration work 
CAMS, Iodide CIMS and SP2 racks deftly installed
HR-AMS and GT-CIMS continued in-lab preparation for installation

Thursday, 5/30 Plans:
06:00 A/C access
Installation/integration work to continue
HR-AMS to install in the a.m.
GT-CIMS to install in the p.m.
13:00 Lab meeting
17:30 A/C access ends

Be sure to secure all gas cylinders on/off A/C
Send pressure system schematics to Richard Wong
Send heater system schematics to Brennan Wehr/Paul Martinez

2019-05-28

Tuesday, 5/28 Acomplishments:
Continued CARE, DLH/DACOM and LARGE integrations
CAMS, AS-TEM, GT-CIMS, HR-AMS, Iodide CIMS, SP2 teams and equipment arrived

Wednesday, 5/29 Plans:
06:00    A/C access
Installation/integration work to continue
13:00    Lab meeting
17:30    A/C access ends

Be sure to secure all gas cylinders on/off A/C
Send pressure system schematics to Richard Wong
Send heater system schematics to Brennan Wehr/Paul Martinez

2019-05-27

Tuesday, 5/28 Plan:
06:00    A/C access
07:00    Visitor Control Center (VCC, Badge Office) opena
17:30    A/C access ends