ATTREX

ATTREX 02/18/14 Daily Schedule
ATTREX  GH Overview:

-Instrument Post-flight activity

-Preparations underway for next flight

Today’s Activities:

-Instrument and Aircraft Post-flight

-Inmarsat Modem troubleshooting all day

Plan for tomorrow, Wednesday:

-0730: Daily GH and ATTREX Leads Mtg in Hangar

-0800 - 1100: Instrument Preflight with aircraft power and Data-IT support

o   Preflight proactivity assumes a Thursday Flight regardless

o   Replacement of Inmarsat Modem in work

ATTREX 02/18/14 Daily Schedule
ATTREX  GH Overview:

-Congratulations to the ATTREX and GH Team for another successful flight.

Takeoff at 1718Z (16Feb) – 0318 local 17Feb’14

Landing at 1059Z (17Feb) – 2159 local

Today’s Post-flight Activities:

-2100 – 0400: GH Crew post-flights aircraft (weight, fuel, engine wash, weigh, de-panel)

o   2130: PCRS, DLH, and UCATS will have post-landing access for Cal. Gas Shutoff

o   Zone-25 and Z-14 (R2) to be removed temporarily after weighing for this access

ATTREX 02/16/14 Daily Schedule
ATTREX  GH Overview:

-Instrument and Aircraft have been preflighted

-Next Flight is tomorrow, Monday, 17Feb.

o   Take-off 0300 ChST, (1700 Z Sunday, 0900 PST Sunday)

o   ~18 hr. duration

Today’s Activities:

-0700: Daily Tag-up of GH Team, ESPO, Science Leads in Hangar

-0830 – 1130: Preflight of Instruments with Aircraft Power and Data-IT support

o   Hands off at 1130.

-0900: T-1 Briefing (Building 18006, Rm 15)

-1900 – 2200: “Day-of-Flight” Inst. Pre-flight activity

ATTREX 02/14/14 Daily Schedule
ATTREX  GH Overview:

-Post-flight Briefing of 1st Science Flight.

-Aircraft post-flight complete – no issues.

-Instruments continue with post-flight data review.

-Next Flight scheduled for Monday, 17Feb. Take-off 0300 local, ~18 hr. duration

The Plan for the remainder of today is:

-Ethernet troubleshooting of Mini-DOAS completed

-Aircraft moved to USAF GH Hangar (#6)

o   No Fire Watch tonight

The Plan for the tomorrow (Saturday) is:

-GH Crew Hard-down Day (no aircraft access)

ATTREX 02/14/14 Daily Schedule

ATTREX GH Overview: -Post-flight Briefing of 1st Science Flight. -Aircraft post-flight complete – no issues. -Instruments continue with post-flight data review. -Next Flight scheduled for Monday, 17Feb. Take-off 0300 local, ~18 hr. duration The Plan for the remainder of today is: -Ethernet troubleshooting of Mini-DOAS completed -Aircraft moved to USAF GH Hangar (#6) o No Fire Watch tonight The Plan for the tomorrow (Saturday) is: -GH Crew Hard-down Day (no aircraft access) -1000: Science Team Photo with CAST and CONTRAST Teams at PGUM. See Jhony Z. e-mail.

ATTREX 02/13/14 Daily Schedule
ATTREX  GH Overview:

-Science Flight #1. Associated Pics attached.

- Congratulations to the entire GH/ ATTREX Team for overcoming one issue after another and beginning Science flights…

o   Our new motto:  “Trust the DOP”

The Plan for the remainder of today is:

-2100: Estimated Landing time

o   2000 (tonight) – 0430 (tomorrow): GH crew will recover the aircraft, engine wash, fuel, weigh, depanel, and post-flight

o   ~2200 (TBD): Access for Zone-25 instruments to turn-off gas…

ATTREX 02/12/14 Daily Schedule
ATTREX  GH Overview:

-Aircraft Pressure Transducer repair and test finished.

-MTP repaired, and Mini-DOAS repaired and in test.

-GH/Science Team supported E/PO visit of 200 Guam H.S. Students today

The Plan for the remainder of today is:

-1400 – 1630: Instrument Pre-flight (if needed) with VTC Power & Data-IT Support

o   Support for Mini-DOAS may extend beyond this time at discretion of Crew

o   Most instruments are expected to remain in their current Pre-flight state

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.