ATTREX 02/12/14 Daily Schedule

ATTREX  GH Overview:

-  Aircraft Pressure Transducer repair and test finished.

-  MTP repaired, and Mini-DOAS repaired and in test.

-  GH/Science Team supported E/PO visit of 200 Guam H.S. Students today

 

The Plan for the remainder of today is:

-  1400 – 1630: Instrument Pre-flight (if needed) with VTC Power & Data-IT Support

  o Support for Mini-DOAS may extend beyond this time at discretion of Crew

  o Most instruments are expected to remain in their current Pre-flight state

ATTREX 02/11/14 Daily Schedule
ATTREX  GH Overview:

-Today’s effort did show good GPS-DOP predictability of GH Nav quality.

-Flight scrub was caused by delay caused by engine restart, a USAF GH Takeoff, and finally (on the runway) by a Hydraulic sensor fault.

Today’s Activities:

-1100 – 1930: 2nd Crew Shift for afternoon activity

o   GH Hydraulic Pressure Sensor replacement and testing

o   Crew requested to remove Z-14 (Heater), Z-22 (MTP Data), & Z-61 (GWAS) Hatches

ATTREX 02/10/14 Daily Schedule
ATTREX  GH Overview:

-Aircraft pre-flight complete – Flight tomorrow early AM

Today’s Activities:

- Aircraft, GHMOF, and Science Instrument Preflight

-Video Crew filmed activity in the Hangar with AAFB escort


The Plan for tomorrow (Tuesday) is:

-2030 – 2330 (tonight): Day-of-Flight Inst. Pre-flight

-0130: T-0 Briefing by Pilots, GH Crew, ATTREX Mission Science, etc.

o   Briefing will be in GH Hangar 4, Room 3 (GH Crew Offices)

-0215: PMOF Staffing

-0230: Engine Start

ATTREX 02/10/14 Daily Schedule

ATTREX  GH Overview:

-Outdoor aircraft Nav/OmniSTAR testing and data analysis continued.

-Next flight proposed.

Today’s Activities:

-OmniSTAR Receiver replaced.

-Outdoor aircraft Nav/OmniSTAR Testing performed this morning and afternoon.

-NAV data being analyzed.

Plan for Today (Monday)

Preflight of Instruments with Aircraft Power and Data-IT support

o   0930 – 1200

Plan for Tomorrow (Tuesday):

o   Day-of-Flight Inst. Pre-flight: 2030 - 2330

ATTREX 02/09/14 Daily Schedule

ATTREX  GH Overview:

- Outdoor aircraft Nav/OmniSTAR testing and data analysis continued.

- Next flight proposed.

 

Today’s Activities:

- OmniSTAR Receiver replaced.

- Outdoor aircraft Nav/OmniSTAR Testing performed this morning and afternoon.

- NAV data being analyzed.

 

The Plan for tomorrow (Monday) is:

- 0700: Daily morning meeting of Leads for GH, ESPO, Science in the Hangar

- Aircraft prep (OmniSTAR installation secured for flight, etc.)

ATTREX 02/07/14 Daily Schedule

ATTREX  GH Overview:

-Outdoor aircraft Nav/OmniSTAR testing and consultation with NGC continues.

 

Today’s Activities:

-Engine Wash performed

-Outdoor aircraft Nav/OmniSTAR Testing performed this morning and afternoon

-Replacement OmniSTAR Receiver arriving tonight at PGUM.


The Plan for tomorrow (Sunday) is:

0700: Daily morning meeting of Leads for GH, ESPO, Science in the Hangar

-Outdoor aircraft Nav/OmniSTAR testing will continue.

ATTREX 02/07/14 Daily Schedule

ATTREX  GH Overview:

-Outdoor aircraft Nav/OmniSTAR testing and consultation with NGC continues.

 

Today’s Activities:

-Engine Wash performed

-Outdoor aircraft Nav/OmniSTAR Testing performed this morning and afternoon

-Replacement OmniSTAR Receiver arriving tonight at PGUM.


The Plan for tomorrow (Sunday) is:

0700: Daily morning meeting of Leads for GH, ESPO, Science in the Hangar

-Outdoor aircraft Nav/OmniSTAR testing will continue.

ATTREX 02/07/14 Daily Schedule

ATTREX  GH Overview:

- After the scrub today, instruments needing off-aircraft testing were removed

- OmniSTAR testing and consultation with NGC and USAF continues.

- Bernie Luna will assume responsibility as onsite ATTREX Proj. Mgr starting tomorrow.

 

Today’s Activities:

- Science Flight scrubbed due to OmniSTAR issues on the aircraft

- OmniSTAR Testing is being performed this afternoon on a USAF GH for comparison info

- AV-6 outdoor OmniSTAR testing continues this evening

ATTREX 02/06/14 Daily Schedule
ATTREX  GH Overview:

-Proceeding to another science flight attempt tomorrow, 0700 Takeoff.


The schedule for the remainder of today is:

-1230: Aircraft returns to Hangar

-Zone-25 will be removed for standard post-flight gas valve turn-off of DLH and HUPCRS instruments

-1700: 2nd-shift Crew arrives

-HUPCRS access as requested with external power

-Access with Crew permission, after they arrive on duty

-Aircraft to remain in pre-flighted condition – no instrument access except as mentioned

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.