ATTREX 02/16/14 Daily Schedule

ATTREX  GH Overview:

-Instrument and Aircraft have been preflighted

-Next Flight is tomorrow, Monday, 17Feb.

o   Take-off 0300 ChST, (1700 Z Sunday, 0900 PST Sunday)

o   ~18 hr. duration

Today’s Activities:

-0700: Daily Tag-up of GH Team, ESPO, Science Leads in Hangar

-0830 – 1130: Preflight of Instruments with Aircraft Power and Data-IT support

o   Hands off at 1130.

-0900: T-1 Briefing (Building 18006, Rm 15)

-1900 – 2200: “Day-of-Flight” Inst. Pre-flight activity

Plan for tomorrow, Monday (Science Flight #2):

-0100: T-0 Briefing (to be held in the GH Crew Area, Hangar)

o   0145: Staff PMOF

-0210: Engine Start

o   0245: Pin-Pull

- ~0300: Taxi and Take-off

- ~2100: Landing (18-hr flight)

-2100 – 0400: GH Crew post-flights aircraft (weight, fuel, engine wash, weigh, de-panel)

o  2130: PCRS, DLH, and UCATS will have post-landing access for Cal. Gas Shutoff

o   Zone-25 and Z-14 (R2) to be removed temporarily after weighing for this access

The Plan for Tuesday is for Aircraft and Instrument Post-flight:

-0900 - 1300: Access to instruments with aircraft power and Data-IT support

o   Avionics Tech will support small panel removal.

o   Any instrument needing Crew support (MMS, CPL) – start at 1100.

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.