Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

2014-07-18

AFRC Overview:

AV-1 Integration and aircraft activity continue

 

AFRC Accomplishments:

Avionics prepped for power

Power to instruments

Hangar IT testing

 

HAMSR and HIRAD successfully powered and transferred data. HIWRAP successfully powered and is troubleshooting an optical connection.

 

AFRC Outlook:

No activity planned for Saturday or Sunday

Monday 0830: AV-1 Outdoor Satcom/GHOC-E Data-IT testing of Instruments

Monday: AV-6 S-HIS and AVAPS Teams arrive, Integration activity

Wednesday: AV-6 CPL team arrives. Instruments fully integrated by COB

Thursday: AV-6 Hangar IT Testing

Friday: AV-6 W&B

 

WFF Monday Schedule:

0730 Badging, if needed

0800 Scan laptops

0900 COMSEC briefing

0930-1100 software downloads/installs if required

1100-1130 eat lunch

1130 Begin satcom testing in GHOC-E. Teams requested in this order: HAMSR, HIRAD, HIWRAP

 

AV-1 outdoor testing will start early (0630 Pacific) in the morning (to stay cool). Data IT performs tasks/checks before working with instrument teams. Ending time will vary with the temperature.

 

The HIWRAP team has made arrangements to be in the AFRC 4840 hangar over the weekend. Teams are reminded that U.S. citizens must be COMSEC-briefed before coming to the hangar unescorted. An Armstrong employee must be the escort to those U.S. citizens who have not yet had the briefing. Foreign nationals always need an Armstrong employee as escort in the hangar.

 

HS3 team members arriving Wallops and having difficulty with badging or entry, call ESPO 757-824-7000.

2014-07-17

Overview:

AV-1 Integration and aircraft activity continue

 

Today’s Accomplishments:

AV-1 Wt & Balance performed

Fueling performed

Avionics prepping for power

 

The Plan for tomorrow (Friday) is:

Continue avionics prep for power (estimated 1-3 hours beginning 0630)

Power to instruments and hangar IT testing of instruments (remainder of day)

 

Outlook:

No activity planned for Saturday or Sunday

Monday +: AV-1 Outdoor Satcom/GHOC-E Data-IT testing of Instrument

Monday +: AV-6 Instrument Teams arrive, Integration activity

 

Excepting Monday, AV-1 outdoor testing will start early (0630) in the morning (to stay cool).

 
Check the next Daily Status for a start time for Monday.

2014-07-16

Overview:

AV-1 Integration and aircraft activity continue on schedule.

 

Today’s Accomplishments:

AV-1 integration activity is complete

o   HAMSR installed

o   HIRAD installed

o   HIWRAP installed

Aircraft ready for Wt. & Balance


The Plan for tomorrow (Thursday) is:

0730: Payload Cage meeting of Leads and PI’s

Wt & Balance

Fuel aircraft and reweigh

Avionics prep for power (see Friday)

Instrument teams requested to remain in Hangar to support Avionics activity

 

The Plan for Friday is:

Hangar IT Testing of instruments (0700 - 1500)

 

Outlook:

No activity planned for Saturday or Sunday

Monday +: AV-1 Outdoor Satcom/GHOC-E Data-IT testing of Instrument

Monday +: AV-6 Instrument Teams arrive, Integration activity

2014-07-15

Overview:

AV-1 Integration and aircraft activity continue on schedule.

 

Today’s Accomplishments:

At WFF, Dana Tanks and Berms setup complete

AV-1 integration activity continues

o   HAMSR installed

o   HIRAD Structural mounting progressing

o   HIWRAP completes SIL Bench Testing

HIRAD completes outdoor sky radiation test

New Daylight Nose Cam wiring begins

Chris and Gerry H. give AFRC “What’s Happening” Presentation


The Plan for tomorrow (Wednesday):

0730 Payload Cage meeting of Leads and PI’s

HIRAD installation on aircraft

HIWRAP installation on aircraft

Hangar IT Testing of instruments (if time permits)

 

The Plan for Thursday:

Hangar IT Testing of instruments (0700 - 0930)

AV-1 Wt/Balance

Fuel & Weigh AV-1

 

Outlook:

Friday all day (beginning at 0700): Hangar IT Testing of instruments

No activity planned for Saturday or Sunday

Monday +: Outdoor Satcom/GHOC-E Data-IT testing of Instruments

2014-07-14

Overview:

HS3 ‘14 begins today at AFRC and WFF.

 

Today’s Accomplishments:

Dana Tanks arrived at WFF

At AFRC, HIWRAP, HIRAD, and HAMSR teams arrived and began pre-integration testing

o   HAMSR passed SIL Bench

o   HIRAD SIL Bench started

COMSEC Training of PI’s at AFRC


The Plan for tomorrow (Tuesday):

0730 Payload Cage meeting of Leads and PI’s

HAMSR installation on aircraft

HIRAD outdoor sky radiation test

HIRAD completes SIL Testing, possible installation

HIWRAP SIL Bench Test

 

The Plan for Wednesday:

Installation of HIWRAP and HIRAD

Begin Hangar IT if time allows

Prep aircraft for Wt./Bal

 

Outlook:

Thursday AM is AV-1 Wt/Balance

Thursday PM is Hangar IT with all instruments

Friday all day: Hangar IT with all instruments

2014-04-28

AFRC UPDATE:

 

AV-6 Completed:
  • TWiLiTE configured for ping test
  • Replaced broken control rod.
AV-6 Goals:
Tuesday Apr 29:
  • TWiLiTE ping test
  • Complete AVAPS support structure installation
  • Payload IT testing
Wednesday Apr 30:
  • Results from TWiLiTE ping test
  • TWiLiTE on A/C Bench testing
  • Payload IT testing

2014-04-25

AFRC UPDATE:

 

AV-6 Completed:

  • TWiLiTE mechanical integration

AV-6 Goals:

Monday Apr 28:

  • TWiLiTE electrical integration
  • Begin AVAPS support structure installation

Tuesday Apr 29:

  • TWiLiTE ping test
  • Complete AVAPS support structure installation

 

2014-04-24

AFRC UPDATE:

 

AV-6 Completed:

  • AVAPS Bench Test
  • Partial TWiLiTE Install

AV-6 Goals:

Friday Apr 25:

  • Complete TWiLiTE Install

2014-04-23

AFRC UPDATE:

 

AV-6 Goals:

Thursday Apr 24:

  • AVAPS Bench Test/Install
  • TWiLiTE Install

Friday Apr 25:

  • AVAPS Bench Test/Install
  • TWiLiTE Install

2014-04-22

AFRC UPDATE:

 

AV-6 Completed:

AVAPS and TWiLiTE instruments arrived.


AV-6 Goals:

Tuesday Apr 22:

  • Unpacking and weighing AVAPS
  • Unpacking and weighing TWiLiTE

Wednesday Apr 23:

  • Installation of AVAPS support structure
  • AVAPS Sil Bench
  • Mechanical integration of TWiLiTE

Pages