Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

Associated content: 
Sub-categories: 

HS3 07/31/14 Daily Schedule

Overview:

   AV-6 Ready for “CST” on Monday (see CST Schedule below)

   AV-1 Ready for Science Team’s return on 11Aug

 Today’s Accomplishments:

   AV-6 Data-IT activity

    o   Ku testing with HS3’14 Ku Transmission Plan

   HDVis Environmental Lab Test successful

ORR (Pacific Time)

Date: 
Thursday, July 10, 2014 - 08:00 - 09:00

HS3 07/30/14 Daily Schedule

Overview:

    AV-1 Ready for CST – Science Team’s on scheduled break from AFRC/WFF

    AV-6 Ready for CST (pic)

 

Today’s Accomplishments:

    AV-6 Data-IT activity

    o   S-HIS Pre-flight complete for CST

AV-1 and AV-6 ready for CSTs (07.30.14)

Don Sullivan sets up Inst. Network Servers (07.30.14)

HS3 07/29/14 Daily Schedule

Overview:

AV-1 Ready for CST – Science Team’s on scheduled break from AFRC/WFF

AV-6 ahead of schedule

HDVis new lens attachment (07.29.14)

S-HIS temporary removal for maintenance (07.29.14)

S-HIS Re-installation (07.29.14)

GHOC-E during AV-6 Outdoor Testing (07.29.14)