Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

Associated content: 

GHOST Engineers (Neil Humpage, Andy Vick) test instrument (2.20.15)

ATTREX 02/20/15 Mission Daily Schedule

Overview:

  • Instruments and aircraft ready for CST on Monday, Flight on Tuesday
  • Note to all Inst. PI’s – please see GHOC show schedule below

Accomplishments:

MMS Nav data wiring change (2.19.15)

ATTREX 02/19/15 Mission Daily Schedule

Overview:

  • Maintenance and Avionics aircraft work continues in preparation for CST
  • CST scheduled – however, all PI’s should look for e-mail at 0800 confirming details

Accomplishments:

  • Maintenance and avionics flight readiness activity continues on aircraft
  • AIITS removed for upload and checkout of new software
  • MMS Nav-data cable modified to reduce noise

Issues/Watch items:

GHOST PIs fill LN2 prior to outdoor testing (2.18.15)

ATTREX 02/18/15 Mission Daily Schedule

Overview:

  • Pre-CST related activity performed – ready for CST Friday.
  • Air vehicle readiness and instrument integration/testing is on schedule.

Accomplishments:

ATTREX 02/04/15 Mission Daily Schedule

Overview:

CAST/ATTREX Instrument integration proceeding as scheduled. GHOST Z-25 installation is behind schedule due to a delay in pallet prep, however the pallet is expected tomorrow.
 
Accomplishments:

  • All Instruments have passed SIL Bench Testing.
  • AIITS Pod completes Environmental Testing
  • MMS, MPT, Hawkeye, NWV, O3, and GWAS are mechanically installed.
  • AIITS fiber installed – Cabin Pres. Test Thursday AM

Concerns / Watch List:

ATTREX 02/05/15 Mission Daily Schedule

Overview:

CAST/ATTREX Instrument integration proceeding as scheduled. GHOST Installation is 2 days behind schedule… currently the only instrument not mounted.
 
Accomplishments:

  • Cabin Pressurization test completed
  • Avionics tie-up of harnesses ongoing
  • AIITS Pod mounted on the wing, preloads almost completed
  • CAST/ATTREX Leads Status/Flight Planning telecom held
  • Final pre-installation work on the GHOST Pallet continuing

Concerns / Watch List:

ATTREX 02/06/15 Mission Daily Schedule

Overview:

  • CAST/ATTREX Instrument integration/test proceeding as scheduled. GHOST Installation has begun in Zone-25 
  • GHOST installation continues Saturday

Accomplishments:

  • AIITS Pod mounting on the wing completed
  • Structural Shear/Bending Analysis review meeting held at NGC
  • Installation of the GHOST Pallet commenced, TAM Mounted and Fairing Cut.

Concerns / Watch List:

ATTREX 02/10/15 Mission Daily Schedule

Overview:

CAST/ATTREX Instrument integration proceeding as scheduled. GHOST mechanical Installation and AIITS Ping Test completed.
 
Accomplishments:

  • GHOST mechanical installation completed (see pic)
  • AIITS Pod structural dynamics (“Ping”) test completed (see pic)

Concerns / Watch List: