Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

ATTREX 02/12/15 Mission Daily Schedule

Overview:

CAST/ATTREX Instrument integration/testing is on schedule. Wt/Bal completed. Outdoor IT Testing tomorrow.
P.I.’s please see revised show-time schedule below…
 
Accomplishments:

  • AIITS Laser re-installed and instrument is working
  • Hangar Data-IT Testing continued

Upcoming Schedule:

  • Tomorrow, Friday (OA and OM Crew support approved for 8 hours)
    • Begin the morning in the Hangar – finish Data IT Testing
    • Prepare for outdoor Satcom Testing at ~0900.
    • 0730 Show-time for: MMS, GHOST, AIITS
    • 0800 Show-time for: Hawkeye
    • 0900 Show-time for all remaining instruments