Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.
Sun | Mon | Tue | Wed | Thu | Fri | Sat |
---|---|---|---|---|---|---|
29 |
30 |
31 |
||||
«
Acceptance Inspection
2013-09-11 - 2014-04-03
»
|
||||||
«
DC-8 at Heavy C Check Facility
2013-11-12 - 2014-03-01
»
|
||||||
«
Corrosion and Flight Control Cables Inspection
2013-11-12 - 2013-12-31
|
|
|
|
|
||
«
Minor Ops Inspection
2013-11-20 - 2014-02-28
»
|
||||||
«
992 Maintenance
2013-11-27 - 2014-01-21
»
|
||||||
«
Maintenance
2013-12-02 - 2013-12-31
|
|
|
|
|
||
«
Maintenance
2013-12-06 - 2014-01-03
|
|
|||||
«
Maintenance
2013-12-10 - 2014-02-21
»
|
||||||
«
Major Ops Inspection
2013-12-16 - 2014-08-18
»
|
||||||
«
Local Flights
2013-11-14 - 2014-01-15
»
|
||||||
«
Reising IIP radar for SWOT
2013-12-01 - 2014-01-15
»
|
||||||
«
NGC Work
2013-12-06 - 2014-06-30
»
|
||||||
|
|
|
|
|
|
|
|
|
|
Local Mexico Flights
2014-01-08 - 2014-01-09
|
ATTREX PI's/872 Team transit to AAFB/Guam
2014-01-10 - 2014-01-12
»
|
||
«
Acceptance Inspection
2013-09-11 - 2014-04-03
»
|
||||||
«
DC-8 at Heavy C Check Facility
2013-11-12 - 2014-03-01
»
|
||||||
«
Minor Ops Inspection
2013-11-20 - 2014-02-28
»
|
||||||
«
992 Maintenance
2013-11-27 - 2014-01-21
»
|
||||||
«
Maintenance
2013-12-10 - 2014-02-21
»
|
||||||
«
Major Ops Inspection
2013-12-16 - 2014-08-18
»
|
||||||
«
Local Flights
2013-11-14 - 2014-01-15
»
|
||||||
«
Reising IIP radar for SWOT
2013-12-01 - 2014-01-15
»
|
||||||
«
NGC Work
2013-12-06 - 2014-06-30
»
|
||||||
|
600-Hr Inspection/Maintenance
2014-01-06 - 2014-04-08
»
|
|||||
Two Micron Lidar
2014-01-06 - 2014-01-31
»
|
||||||
|
|
|
||||
«
ATTREX PI's/872 Team transit to AAFB/Guam
2014-01-10 - 2014-01-12
|
California Science Flights
2014-01-13 - 2014-01-22
»
|
|||||
«
Acceptance Inspection
2013-09-11 - 2014-04-03
»
|
||||||
«
DC-8 at Heavy C Check Facility
2013-11-12 - 2014-03-01
»
|
||||||
«
Minor Ops Inspection
2013-11-20 - 2014-02-28
»
|
||||||
«
992 Maintenance
2013-11-27 - 2014-01-21
»
|
||||||
«
Maintenance
2013-12-10 - 2014-02-21
»
|
||||||
«
Major Ops Inspection
2013-12-16 - 2014-08-18
»
|
||||||
«
600-Hr Inspection/Maintenance
2014-01-06 - 2014-04-08
»
|
||||||
«
Local Flights
2013-11-14 - 2014-01-15
|
|
|
|
|||
«
Reising IIP radar for SWOT
2013-12-01 - 2014-01-15
|
|
|
|
|||
«
Two Micron Lidar
2014-01-06 - 2014-01-31
»
|
||||||
«
NGC Work
2013-12-06 - 2014-06-30
»
|
||||||
|
|
872 ATTREX Ferry Flight to AAFB/Guam
2014-01-15 - 2014-01-16
|
|
|
||
|
||||||
«
Acceptance Inspection
2013-09-11 - 2014-04-03
»
|
||||||
«
DC-8 at Heavy C Check Facility
2013-11-12 - 2014-03-01
»
|
||||||
«
Minor Ops Inspection
2013-11-20 - 2014-02-28
»
|
||||||
«
992 Maintenance
2013-11-27 - 2014-01-21
|
|
|
|
|
||
«
Maintenance
2013-12-10 - 2014-02-21
»
|
||||||
«
Major Ops Inspection
2013-12-16 - 2014-08-18
»
|
||||||
«
600-Hr Inspection/Maintenance
2014-01-06 - 2014-04-08
»
|
||||||
«
Two Micron Lidar
2014-01-06 - 2014-01-31
»
|
||||||
«
California Science Flights
2014-01-13 - 2014-01-22
|
|
|
|
|||
«
NGC Work
2013-12-06 - 2014-06-30
»
|
||||||
|
|
ATTREX Deployment Guam
2014-01-21 - 2014-03-14
»
|
||||
|
|
|
|
|
||
1 |
||||||
|
|
Iceland
2014-01-28 - 2014-02-06
»
|
||||
«
Acceptance Inspection
2013-09-11 - 2014-04-03
»
|
||||||
«
DC-8 at Heavy C Check Facility
2013-11-12 - 2014-03-01
»
|
||||||
«
Minor Ops Inspection
2013-11-20 - 2014-02-28
»
|
||||||
«
Maintenance
2013-12-10 - 2014-02-21
»
|
||||||
«
Major Ops Inspection
2013-12-16 - 2014-08-18
»
|
||||||
«
600-Hr Inspection/Maintenance
2014-01-06 - 2014-04-08
»
|
||||||
«
Two Micron Lidar
2014-01-06 - 2014-01-31
|
|
|||||
«
ATTREX Deployment Guam
2014-01-21 - 2014-03-14
»
|
||||||
«
NGC Work
2013-12-06 - 2014-06-30
»
|
||||||
|
|
|
|
|