Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

SOLVE II Mission Schedule

October 2002

Thursday October 17

  • ICATS Planning Meeting at NASA/Dryden

Wednesday October 23 & Thursday October 24

  • VINTERSOL Planning Meeting in Brussels

Thursday October 31

  • ECR's Complete

 


November 2002

Monday November 11

  • Leonid Payload Integration Begins

Thursday November 14

  • Roll-out
  • Safety Brief

Friday November 15

  • Shakedown Flight - 2.0 Hours

Saturday November 16

  • Experimenter Test Flight - 2.0 Hours

Sunday November 17

  • Leonid Transit to Field

Monday November 18

  • SOLVE II Payload Integration Begins
  • Principal Investigators Arrive

Wednesday November 20

  • Leonid Transit to Dryden Flight Research Center

Thursday November 21

  • Leonid Payload Download
  • SOLVE II Payload Upload Begins

 


December 2002

Wednesday December 4

  • Power-up Check

Friday December 6 - Tuesday December 10

  • AGU Meeting

Monday December 9 - Friday December 20

  • Laser Alignments and Calibrations

Monday December 9

  • Roll-out

Tuesday December 10

  • Shakedown Flight - 3.0 Hours

Wednesday December 11

  • Science Team Meeting in ISF

Thursday December 12

  • Safety Briefing

Friday December 13

  • First Experimenter Test Flight - 2.0 Hours

Tuesday December 17

  • Second Experimenter Test Flight - 2.0 Hours

Thursday December 19

  • Third Experimenter Test Flight - 8.0 Hours

Friday December 20

  • SOLVE II Principal Investigators Depart for Holiday Break

 


January 2003

Thursday January 2 - Tuesday January 7

  • Laser Alignment and Calibrations

Thursday January 2

  • Earliest Day SOLVE II Principal Investigators Return

Saturday January 4

  • Back-up Experimenter Test Flight - 8.0 Hours

Monday January 6

  • Cargo Flight from DFRC to Kiruna

Wednesday January 8

  • Deploy to Kiruna

Thursday January 9

  • Arrive in Kiruna

Sunday January 12

  • First Science Flight - 6.0 Hours

Tuesday January 14

  • Science Flight - 6.0 Hours

Thursday January 16

  • Science Flight - 8.0 Hours

Saturday January 18

  • Science Flight - 10.0 Hours

Sunday January 19

  • Down Day

Tuesday January 21

  • Science Flight - 10.0 Hours

Thursday January 23

  • Science Flight - 10.0 Hours

Saturday January 25

  • Science Flight - 10.0 Hours

Monday January 27

  • Science Flight - 10.0 Hours

Wednesday January 29

  • Science Flight - 10.0 Hours

Thursday January 30

  • Down Day

 


February 2003

Saturday February 1

  • Science Flight - 10.0 Hours

Monday February 3

  • Last Science Flight - 10.0 Hours

Thursday February 6

  • DC-8 Transit to DFRC