2016-04-17

PLAN FOR 4/17:  (escroll to the bottom for an update from Osan AB)
AFRC DC-8 KORUS Mission
4/17:  Sunday
0700-1200 Lab access only

PLAN FOR 4/18:  Monday - Instrument Check Flight
0600-1030 Aircraft Access
1030 Flight Briefing –
All Flyers must be present or have representation
1145 DC-8 Doors Close
1200 Take off 
1515 Land
1530 – 1700  Limited Aircraft access

**The following individuals need Egress Training on Monday prior to flights per current records.**
Jack Dibb
Markus Mueller
Michael Agnew

*See Matt Berry for assistance!!*

4/19: Tuesday
0700-1700  Aircraft and Lab Access

4/20: Wednesday
AFRC Safety Stand Down Day – NO Aircraft Access

NOTES:
TOOL CONTROL = All Tools must be returned and signed off before each flight
INSPECTION = All Instruments must be secured and inspected before flight.
Weight/Balance = Any times removed or installed on the aircraft must be documented for weight and balance on the log sheet posted in the aircraft.

END OF THE DAY REPORT:
DC-8: 4/16
Instrument work continued throughout the day in preparation for Monday test flight.   
•  Lab meeting 1300 every day except Saturday and Sunday.

 LaRC B200: (by Taylor Thorson)
Good news. The overweight/ferry tank test flight went off without a hitch today. We are preparing to begin the ferry flight on Monday 4/18 to California. We are still planning on going the southern route and arriving in Korea on 24 April. 
*****************
UPDATE FROM OSAN AB:

GOOD NEWS:
The base has granted ration card privileges to all US citizens. ESPO will printout the necessary forms and distribute them upon your arrival. You must bring this form, together with your passport (or passports if you had your passport renewed during the  approval process) to the Pass & Registration Office (see UPON YOUR ARRIVAL below); with this number of Ration cards available it should be easy to accommodate everyone in our mission to purchase groceries at the base commissary.

LOGISTICS:
Our sea surface shipment arrived, the cargo has been unloaded (except for DC-8 equipment).
We’ll be able to accommodate everyone in building 1187. The office space setup there is almost complete (see attached photo). Team seating assignments will be emailed in a few days (an email about this will soon follow up.)
The ISP run into some delays laying the fiber optic cable to our building, it is expected to be up and running by the end of this week.
Buildings 1161 office space setup is complete. This building will be utilized by both B200 aircraft, crews, and instrument teams.

BADGING:
Osan AB Security Services has sent a request up their chain of command to have the Pass & Registration Office open exclusively for KORUS-AQ personnel on April 26th in order to expedite the issuance of 37EK Base ID cards.
We have a lot of people to process that day, so we appreciate your patience. New arrivals will be broken up into smaller groups in order to minimize the wait. Details will be given that morning.

UPON YOUR ARRIVAL:
Remember to keep ESPO aware of your arrival: osan@espo.nasa.gov 
We will meet in the lobby of the Turumi Lodge at 0740 the morning after your arrival. ESPO will distribute some required documentation as appropriate and from here, we’ll take you to the pass and registration office to get your 37EK Osan ID card (and Ration Card authorization as needed.)
If planning to bring vehicles on base, bring the additional documentation: driver license, car registration, insurance information.

PERSONAL CARS/VEHICLES
Personnel planning to bring their vehicles on base must bring the paperwork as indicated above.
It is highly recommended that for the first time, the vehicles be parked off-base (there is a parking garage within walking distance from the main gate). The driver may then enter the base via the Main Gate and bring the above documentation to the Pass & Registration office. A temporary 30-day pass will be issued at that time. Please refer to the information package for details about gates’ hours, etc.

2016-04-16

PLAN FOR 4/16
AFRC DC-8 KORUS Mission
4/16:  Saturday
0700-1700  Aircraft and Lab Access

4/17:  Sunday
0700-1200 Lab access only

4/18:  Monday - Instrument Check Flight
0600-1030   Aircraft Access
1030     Flight Briefing –
All Flyers must be present or have representation
1145     DC-8 Doors Close
1200    Take off
1515    Land
1530 – 1700  Limited Aircraft access

4/19: Tuesday
0700-1700  Aircraft and Lab Access

NOTES:
TOOL CONTROL = All Tools must be returned and signed off before each flight
INSPECTION = All Instruments must be secured and inspected before flight.
Weight/Balance = Any times removed or installed on the aircraft must be documented for weight and balance on the log sheet posted in the aircraft.

END OF THE DAY REPORT:
DC-8:
Engineering Check Flight Complete!!
Aircraft in good shape

•  Lab meeting 1300 every day except Saturday and Sunday.

 LaRC B200: (by Taylor Thorson)
We were unable to get the overweight flight accomplished today. Maintenance is working tirelessly for a possible flight tomorrow. If the flight does not go tomorrow (Saturday), we will slip the flight until Monday and leave for the deployment on Tuesday (sliding everything one day to the right). 

Good news:
Install of ferry tanks completed
Weight and balance completed
Partial transfer test of fuel completed
Winds and weather favorable for Hawaii transit

2016-04-15

PLAN FOR 4/15
Friday:  
0700-1200: DC-8 outside 
   Engine Run
   Pressurization check
   Wt / Balance - (Aircraft Inside Hangar) PI tool boxes in overhead to be included for Wt/Balance
1200-1400     Aircraft Pre-Flight
1400-1530     Engineering flight
1600-1700     Post-flight inspection
                        (Very Limited access)

NOTES:
TOOL CONTROL = All Tools are to be returned and signed off before flight
INSPECTION=All Instruments installed, secured and inspected before flight.
1000 & 1430  ROK Security Brief–AFRC/KORUS

4/16: Saturday
0700-1700    Aircraft Access

4/17: Sunday 
0700-1200    Lab access only

4/18: Monday’s science flight takeoff time is 1200.

2016-04-14

PLAN FOR 4/14
0700 - 1200: Instrument Integration outside CIT-CIMS, DA-COM, DIAL, GT-CIMS, K-ACES, K-CIMS, LARGE and WAS.
 
NOTE:
Thursday
0700-1200 Aircraft will stay outside Wednesday overnight   
Second Half of the day will be aircraft maintenance.
 
Friday: 
0700-1200 Instrument access
1400-1530 Shakedown flight
1600-1700 Post-flight inspection
 
There will be Saturday aircraft access 0700-1700 and Sunday will be lab access only.
Monday’s science flight takeoff time is 1200.
END OF THE DAY REPORT:
DC-8:
CAFS:  Ready for calibration and inspection.
CIT-CIMS:  Calibrating. Pressure Relief Ready for test
DA-COM: Working on front pit
DIAL:  Ready for Cal test continues
GT-CIMS:  Power test complete
K-ACES:  Installed.  Software updates and test underway – ready for probe
K-CIMS:  Ready for Inlet probe.
LARGE:  Ready for Power check
WAS: Canisters ready
 
•  Lab meeting 1300 every day except Saturday and Sunday.
 
LaRC B200: (by Lucille Crittenden) 
Quick status on today’s KORUS activities:
A one hour operational check flight was conducted this morning to give the pilots more familiarity and checkout with the new avionics.
HF radio was in-op and must/will be fixed before deployment.
AirMods began work around 1400 today for installation of the external fuel tanks and will work late this evening.
Hope to do a checkout flight with the external fuel tanks either Friday afternoon or Saturday morning.  Still on track for an 18 April transit.

2016-04-13

PLAN FOR 4/13
0700 - 1700: Instrument Integration CAFS, CIT-CIMS, DIAL, GT-CIMS, K-ACES, K-CIMS, K-PTR-MS and LARGE.
NOTE:
Wednesday
0600 the plane will go outside for DIAL calibrations. 
0700 – 1700 Instrument access.
Thursday
May also involve outdoor calibrations TBD.            
Half of the day will be aircraft maintenance.  Time TBD.
Friday: 
0700-1200 Instrument access
1400-1530 Shakedown flight
1600-1700 Post flight instrument inspection
 
There will be Saturday aircraft access 0700-1700 and Sunday will be lab access only.
Monday’s science flight takeoff time is 1200.

END OF THE DAY REPORT:
DC-8:
CAFS:  Ready for calibration and inspection.
CIT-CIMS:  Calibrating.
DIAL:  Ready for Cal test tomorrow.
GT-CIMS:  Ready for power.
K-ACES:  Installed.  Ready for probe.
K-CIMS:  Ready for probe.
K-PTRMS:  Installed.  Ready for probe.
LARGE:  Wing pod installed.
 
•  Lab meeting 1300 every day except Saturday and Sunday.
 
LaRC B200: (by Lucille Crittenden) 
•  An ESRR (Experimental Systems Readiness Review) was held today and almost all of the action items were checked off; another ESRR (probably virtual) will be held in Korea after the instruments are re-installed and prior to an ICF in order to complete check-off of all ESRR items
•  Science instruments are being removed this afternoon and evening in preparation for pack-up for shipment
•  QA is continuing with closeout of action items
•  An ops check flight will be conducted tomorrow morning to allow more pilot familiarity with the new avionics
•  AirMods will arrive around mid-day tomorrow and begin installation of the external fuel tanks

 

2016-04-11

PLAN FOR 4/12
0600 - 1700: Instrument Integration CIT-CIMS, GT-CIMS, K-ACES, K-CIMS, and K-PTR-MS.

END OF THE DAY REPORT:
DC-8:
CIT-CIMS: Installed.
GT-CIMS:  Ready for power check.
K-ACES:  Installed.
K-CIMS:  Ready for power check.
K-PTRMS:  Installed.
Several instruments have open issues and documentation to complete prior to Friday shake down flight.
NOTES:
•  Lab meeting 1300 every day except Saturday and Sunday.
 
LaRC B200: (by Lucille Crittenden) 
•  The science instruments were installed on the aircraft, finishing up just after noon today.
•  Due to inspections still to complete and a lot of paperwork still to close out , an ICF today was not possible. Scientists were posed to do more ground checks to verify their systems this afternoon.
•  An ICF will be conducted once the aircraft reaches Korea.
•  Current plan is to remove the science instruments and begin their pack up tomorrow afternoon.
•  AirMods will arrive mid-morning on Wednesday to start the fuel tank installation which will take approximately 2 days. Hope to be able to get a check flight with the external tanks on Friday.
•  At this time, it still looks like a transit date of 18April.


 

2016-04-11

PLAN FOR 4/11:
AFRC DC-8
0700 - 1700:  Instrument Integration CAFS, CIT-CIMS, GT-CIMS, K-ACES, K-AMS, K-CIMS, and K-PTR-MS.

LaRC B200: (by Lucille Crittenden) 
Most of Geo-TASO instrumentation was installed yesterday and they have been installing MOS today.  All seems to be going well so far – potential for ICF tomorrow (Monday) afternoon!


 

2016-04-10

Lab access only. CAFS, CIT-CIMS, DIAL, GT-CIMS, HR-AMS, K-ACES, K-AMS, K-CIMS, K-PTR-MS, and PTR-MS.
 

2016-04-09

PLAN FOR 4/9:
0700 - 1700: Instrument Integration CAFS, CIT-CIMS, DIAL, GT-CIMS, HR-AMS, K-ACES, K-AMS, K-CIMS, K-PTR-MS, and PTR-MS.

END OF THE DAY REPORT:
DC-8:
CAFS: Rack shared with K-ACES will be ready Monday.
CIT-CIMS: Installed.
DIAL: Ready for laser calibration 4/13.
GT-CIMS:  Ready for power check 4/9.
HR-AMS:  Ready for power check 4/9.
K-ACES:  Lab work this weekend.  Plan to install Monday.
K-AMS: Installed. Ready for calibration.
K-CIMS:  Ready for power 4/9.
K-PTRMS:  Plan to install Monday.
PTR-MS:  Power check complete.
NOTES:
•  Lab meeting 1300 every day except Saturday and Sunday.
•  If you are working on the plane near HR-AMS, please turn off your cell phone, the signal causes interference.
 
LaRC B200: (by Lucille Crittenden) 
Great news from the UC-12 team today!!
•We just finished the Flight Readiness Review minutes ago.  The pilots are preparing to fly the Functional Check flight within the hour!
•Once I receive word from the pilots after the completion of the FCF (anticipate a 2 hour flight), I will send out another email later this evening giving the Go/No-Go decision on starting instrument installation in the morning.  Kudos to everyone on a fantastic job reaching this milestone!
Update from Luci Crittenden
Just got word from Rick that the FCF was a success and 95% complete. A few squawks and items to address, a lot of which can be done with ground checks and the rest on the ICF. That being said, all is a "GO" for instrument installation to begin tomorrow morning!

2016-04-08

PLAN FOR 4/8

0700 - 1700: Instrument Integration 4STAR, CAFS, CIT-CIMS, DIAL, GT-CIMS, HR-AMS, K-ACES, K-AMS, K-CIMS, K-PTR-MS, K-SP2, LARGE, PTR-MS, and TD-LIF.

END OF THE DAY REPORT:
DC-8:
4STAR:  Installed.  Power check done.
CAFS:  NADIR system installed.  Ready for electrical check.  Rack shared with K-ACES will be ready Monday.
CIT-CIMS: Cabling, plumbing and power complete.
DIAL: Ready for laser calibration 4/13.
GT-CIMS:  Installed and ready for power.
HR-AMS:  Calibrating.  Ready for power check tomorrow.
K-ACES:  Just arrived.
K-AMS: Installed. Inlet work and leak check underway.
K-CIMS:  Installed.
K-PTRMS:  Wiring and cabling underway.
K-SP2:  Installed.  Need new data acquisition card.
LARGE: Installed.
PTR-MS:  Installed.  Ready for power.
TD-LIF:  Installed.  Ready for power check.
NOTES:
•  Lab meeting 1300 every day except Saturday and Sunday.
•  If you are working on the plane near HR-AMS, please turn off your cell phone, the signal causes interference.

LaRC B200: (by Lucille Crittenden) 
Sealant  & pressurization work continued today 4/7
1.  More sealant was pumped in and is now drying.  A pressurization check will be conducted in the morning.
2.  If the pressurization check is successful, the dash will be re-installed and there is hopes of conducting an FRR (Flight Readiness Review) tomorrow afternoon
3.  If  1. and 2. are accomplished in a timely manner, there is a chance of conducting the FCF (Functional Check Flight) late tomorrow afternoon
 
Following a successful check flight, MOS & GEOTASO integration teams are standing by to begin installation on or before Saturday, April 9th
 
Look-ahead schedule is listed below:
Experimental Readiness Review and Instrument check Flight on Monday 4/11
Download instruments on Tuesday 4/12
Ferry tank upload on Wednesday 4/13
Ferry Tank Characterization Flights 4/14-4/16
Transit to Korea 4/18
Arrive Korea 4/26
Media Brief at Osan 4/29
Begin Mission Ops 5/2
 