HS3 08/07/13 Daily Schedule

Forecast Dry Run; August 6-16; See email sent to list serve on 7/30/13, titled 'HS3 Dry Run 2013'.

Please Note: Transits next week  are planned for takeoff at ~7 pm PDT; land ~0800 EDT. There is a possibility of a longer flight due to weather, science goals, or range conflicts. Please plan accordingly. See GHOC and GHOC-E Instrument Team Staffing notes below.

DFRC UPDATE:
AV-6 Goals:

Pending: Nose camera lens installation and checkout

AV-1 Completed:

Instrument Post/Pre-flight and Aircraft Preflight

AV-1 Goals:

Pending: Nose camera lens installation and checkout

Thursday August 8:  Range Flight

PIs not required

Engine start 0600

Take off 0700

Landing 1200

Friday August 9: shipment prep

WFF UPDATE:
AV-1 Goals:

Thursday August 8:   Range Flight

PIs in GHOC-E 0830 EDT

Engine start 0900

Take off 1000

Landing 1500

 

Note: GHOC-E POR Staffing is optional after Takeoff + 2 hrs and prior to Landing – 2hrs, with the exception of any science or test activity (such as Drop Sonde launches, etc).

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.