HS3 07/29/13 Daily Schedule

DFRC UPDATE:
AV-1 Completed:

Pending:   new camera lens for nose camera

AV-6 Completed:

Monday July 29 - pre-CST

AV-6 Goals:

Tuesday July 30  – CST, engine start 0700, no PI's required

Wednesday July 31 - instrument pre-flight and aircraft pre-flight

Thursday August 1 - Range flight, 0630 takeoff

WFF UPDATE:
AV-6 Completed:

Monday July 29 - pre-CST

AV-6 Goals:
Tuesday July 30  – CST, engine start 1000, PI's in GHOC 0930 EDT
Thursday August 1 - Range flight, 0930 takeoff

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.