HS3 07/25/13 Daily Schedule

DFRC UPDATE:
AV-1 Completed:

Thursday July 25 - removed EIPs 1/6 for firmware update

Pending:   new camera lens for nose camera, EIP firmware

AV-6 Completed:

Thursday July 25 - Outdoor Payload-IT testing and in-hangar troubleshooting

AV-6 Goals:

Friday July 26 – IT/Comm troubleshooting, 0600-1430 (no PI's needed)

Saturday - no PI activities

Sunday - no PI activities

Monday - pre-CST PI's arrive 0700 PDT

WFF UPDATE:
AV-6 Completed:

Thursday July 25 -  Outdoor Payload-IT testing

AV-6 Goals:

Friday July 26  -  IT/Comm troubleshooting, 0900-1730 (no PI's needed)

Saturday - no PI activities

Sunday - no PI activities

Monday - pre-CST PI's arrive 1000 EDT

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.