MMS, MTP, SSFR and GWAS are installed on the aircraft.
12/10 Accomplishments:
DLH completed environmental and SIL Bench tests
PCRS began mechanical prep for shake tests
Identified clearance issues for pump deck and power/data system installation
Identified mounting brackets for Picarro instrument
GWAS Identified suitable lab space for canister sample analysis work
12/11 Plans:
NOAA Water Vapor completion of shake test
UCATS & Mini-DOAS SIL Bench tests
NOAA Water Vapor, UCATS & mini-DOAS installation for payload hangar IT testing
PCRS continue working on mechanical installation issues (match drill pallet and install inserts)
Hawkeye continue working on starboard wing mounting issues
GWAS begin getting analysis lab set up
Individual and combined payload hangar IT testing to begin on 12/12
ATTREX system hangar & outdoor testing (iridium) to begin on 12/17