PLAN FOR 4/14:
0700 - 1200: Instrument Integration outside CIT-CIMS, DA-COM, DIAL, GT-CIMS, K-ACES, K-CIMS, LARGE and WAS.
NOTE:
Thursday
0700-1200 Aircraft will stay outside Wednesday overnight
Second Half of the day will be aircraft maintenance.
Friday:
0700-1200 Instrument access
1400-1530 Shakedown flight
1600-1700 Post-flight inspection
There will be Saturday aircraft access 0700-1700 and Sunday will be lab access only.
Monday’s science flight takeoff time is 1200.
END OF THE DAY REPORT:
DC-8:
CAFS: Ready for calibration and inspection.
CIT-CIMS: Calibrating. Pressure Relief Ready for test
DA-COM: Working on front pit
DIAL: Ready for Cal test continues
GT-CIMS: Power test complete
K-ACES: Installed. Software updates and test underway – ready for probe
K-CIMS: Ready for Inlet probe.
LARGE: Ready for Power check
WAS: Canisters ready
• Lab meeting 1300 every day except Saturday and Sunday.
LaRC B200: (by Lucille Crittenden)
Quick status on today’s KORUS activities:
A one hour operational check flight was conducted this morning to give the pilots more familiarity and checkout with the new avionics.
HF radio was in-op and must/will be fixed before deployment.
AirMods began work around 1400 today for installation of the external fuel tanks and will work late this evening.
Hope to do a checkout flight with the external fuel tanks either Friday afternoon or Saturday morning. Still on track for an 18 April transit.