KORUS-AQ 04/06/16 Mission Daily Schedule

PLAN FOR 4/6:

0700 - 1700: Instrument Integration HR-AMS, CAMS, LARGE, DIAL, K-AMS, K-SP2, PTR-MS, K-CCN, CAFS, CIT-CIMS, 4STAR, TD-LIF, NOxyO3, K-CIMS, GT-CIMS

END OF THE DAY REPORT:
DC-8:
HR-AMS:  Instrument installed.  Plumbing underway.
CAMS: Instrument installed.
LARGE: Installed.  Working on wing tip probe.
DIAL: Ready for laser calibration 4/13.
K-AMS: Installed.  Ready for power.
K-SP2:  Installed.  Ready for power.
PTR-MS:  Ready to install on Wednesday
K-CCN:  Installation underway.
CAFS:  Ready to install into rack.
CIT-CIMS:  Inlet and plates installed.  Cabling and plumbing underway.  Space issue with TD-LIF being worked.
4STAR:  instrument working, populating rack.
TD-LIF:  Uploaded
NOxyO3:  Plumbing for forward port underway.
K-CIMS:  Just arrived.  Ready to install tomorrow.
GT-CIMS:  Just arrived.  Ready to install tomorrow.
NOTES:
•  Lab meeting 1300 every day except Saturday and Sunday.

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.