HS3 09/11/13 Daily Schedule

WFF UPDATE (all times EDT):

AV-6 Goals:
Thursday Sep 12:
0800-1000 Instrument & IT Preflight for Potential Fri Flight
Friday Sep 13:  Science Flight #8 (target P34L)
0530 PIs staff GHOC-E
0600 Engine Start
0700 Takeoff

 

Saturday Sep 14:
0800 Landing Science Flight #8

 

 

AV-1 Goals:
Thursday Sep 12:  Maintenance Period, No Instrument Access
Friday Sep 13:  Maintenance Period, No Instrument Access
Saturday Sep 14:  Maintenance Period, No Instrument Access

* Next possible AV-1 flight is NET Mon Sep 16

Science Team:
Thursday Sep 12:
0830 and 2030 Forecast briefings
1530 COMSEC Brief

 

Friday Sep 13:

0830 and 2030 Forecast briefings

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.