Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.
Overview:
AV-1 & AV-6 on schedule
AV-6 Range Flight this Wed.
Today’s Accomplishments:
AV-6 CST Completed successfully (Camera Pics)
HS3 Dry Run started
Plan for Tomorrow (Tuesday):
0630: Fuel aircraft
0730 – 0930: Pre-flight Instruments
o A/C Power and Data-IT support
o All AV-6 Instr. P.I.’s in Hangar
0800 PDT (1100 EDT) Dry Run Continues
o 877-217-8791 (3581543#)
o GH Pilot(s) requested to participate
Aircraft Preflight
1300 PDT: T-1 Briefing for Range Flt.
o Bldg. 4811, Room 111 at AFRC
o 844-467-6272 (961190#)
Plan for Wednesday:
0500 PDT: T-0 Preflight Briefing
o Bldg. 4840, Rm 113A at AFRC
o 844-467-6272
0530 PDT: Crew in GHOC (0830 PI’s in GHOC-E)
0545 PDT: Engine Start
0630 PDT: Takeoff for ~5-6 hr flight
0800 PDT (1100 EDT): Dry Run continues
Outlook:
Thursday: Contingency for Range Flight
o Postflight Instruments
Friday – Sun: No Activity
Monday 11Aug: AV-1 Team’s arrive for CST/Range Flt.