Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

HS3 07/31/14 Daily Schedule

Overview:

   AV-6 Ready for “CST” on Monday (see CST Schedule below)

   AV-1 Ready for Science Team’s return on 11Aug

 Today’s Accomplishments:

   AV-6 Data-IT activity

    o   Ku testing with HS3’14 Ku Transmission Plan

   HDVis Environmental Lab Test successful

   HDVis lens refocus / camera reassembly

The Plan for Tomorrow (Friday):

   0730: GH Leads Mtg in Payload Cage

   GH Crew begins AV-6 CST Preflight activity

   No AV-6 Science/P.I. Activity at AFRC/WFF

   No HS3 Daily Status Report will be issued tomorrow.

 Outlook Next Week:

   Monday (4Aug): AV-6 CST (all times PDT):

    o   0745: Pre-Brief Mtg. (see email for phone #)

    o   0830: Crew & P.I.’s staff GHOC

      -  1130 EST: GHOC-E Payload Team Staffing

      -  GHOC to GHOC-E Comm (see email for phone #)

    o   0930: Engine Start

      -  Expect CST to take ~2 hours

 Tuesday (5Aug): AV-6 Preflight of Inst’s/Aircraft

 Wednesday (6Aug): AV-6 HS3 Range Flight

 

 Thursday (7Aug): Backup date for AV-6 Range Flight