Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.
Overview:
AV-6 Ready for “CST” on Monday (see CST Schedule below)
AV-1 Ready for Science Team’s return on 11Aug
Today’s Accomplishments:
AV-6 Data-IT activity
o Ku testing with HS3’14 Ku Transmission Plan
HDVis Environmental Lab Test successful
HDVis lens refocus / camera reassembly
The Plan for Tomorrow (Friday):
0730: GH Leads Mtg in Payload Cage
GH Crew begins AV-6 CST Preflight activity
No AV-6 Science/P.I. Activity at AFRC/WFF
No HS3 Daily Status Report will be issued tomorrow.
Outlook Next Week:
Monday (4Aug): AV-6 CST (all times PDT):
o 0745: Pre-Brief Mtg. (see email for phone #)
o 0830: Crew & P.I.’s staff GHOC
- 1130 EST: GHOC-E Payload Team Staffing
- GHOC to GHOC-E Comm (see email for phone #)
o 0930: Engine Start
- Expect CST to take ~2 hours
Tuesday (5Aug): AV-6 Preflight of Inst’s/Aircraft
Wednesday (6Aug): AV-6 HS3 Range Flight
Thursday (7Aug): Backup date for AV-6 Range Flight