Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.
Overview:
AV-1 Integration and aircraft activity continue on schedule.
Today’s Accomplishments:
At WFF, Dana Tanks and Berms setup complete
AV-1 integration activity continues
o HAMSR installed
o HIRAD Structural mounting progressing
o HIWRAP completes SIL Bench Testing
HIRAD completes outdoor sky radiation test
New Daylight Nose Cam wiring begins
Chris and Gerry H. give AFRC “What’s Happening” Presentation
The Plan for tomorrow (Wednesday):
0730 Payload Cage meeting of Leads and PI’s
HIRAD installation on aircraft
HIWRAP installation on aircraft
Hangar IT Testing of instruments (if time permits)
The Plan for Thursday:
Hangar IT Testing of instruments (0700 - 0930)
AV-1 Wt/Balance
Fuel & Weigh AV-1
Outlook:
Friday all day (beginning at 0700): Hangar IT Testing of instruments
No activity planned for Saturday or Sunday
Monday +: Outdoor Satcom/GHOC-E Data-IT testing of Instruments