Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.

 

HS3 07/15/14 Daily Schedule

Overview:

AV-1 Integration and aircraft activity continue on schedule.

 

Today’s Accomplishments:

At WFF, Dana Tanks and Berms setup complete

AV-1 integration activity continues

o   HAMSR installed

o   HIRAD Structural mounting progressing

o   HIWRAP completes SIL Bench Testing

HIRAD completes outdoor sky radiation test

New Daylight Nose Cam wiring begins

Chris and Gerry H. give AFRC “What’s Happening” Presentation


The Plan for tomorrow (Wednesday):

0730 Payload Cage meeting of Leads and PI’s

HIRAD installation on aircraft

HIWRAP installation on aircraft

Hangar IT Testing of instruments (if time permits)

 

The Plan for Thursday:

Hangar IT Testing of instruments (0700 - 0930)

AV-1 Wt/Balance

Fuel & Weigh AV-1

 

Outlook:

Friday all day (beginning at 0700): Hangar IT Testing of instruments

No activity planned for Saturday or Sunday

Monday +: Outdoor Satcom/GHOC-E Data-IT testing of Instruments