ATTREX 12/16/12 Daily Schedule

12/16 Accomplishments:
HP/PCRS solved their problems and the system is working properly
UCATS continued system check out work
GWAS continued lab set up and check out and canister cleaning

12/17 Plans:
Perform PCRS environmental chamber test
Reinstall FCDP power/data box on zone 25 pallet
Install Mini-DOAS and perform telescope alignment

 

Disclaimer: This material is being kept online for historical purposes. Though accurate at the time of publication, it is no longer being updated. The page may contain broken links or outdated information, and parts may not function in current web browsers. Visit https://espo.nasa.gov for information about our current projects.